background image

3

OPTIONAL ITEMS

3

PRE-INSTALLATION TEAR DOWN

FAUCETS

SHAMPOO BOX

SHOWER BENCH

TIME REQUIRED

8-16 HRS

This shower system is designed to be installed on a bare floor. It is necessary for any existing shower to be completely removed.  

Tear out and remove all old material to expose the 2 x 4 wall studs. Clean up the shower area, removing all dust and old material from the area.

4

DRY-FITTING THE PAN

TIME REQUIRED

½ to 1 HR

It is easier to check alignment of studs and pan without the drain installed into the pan. Place the pan in the planned position. Check to see that the spacing 

between the pan and 2 x 4 studs are flush. Some shims may be required to plumb walls with the pan. By screwing in the 1/4” cement board the metal flange 

will pull fast to the studs, and will secure the metal pan in place. 

(diagram 1)

With the pan in position, check to make sure the 2” drain pipe is in the center of the pan drain hole. 

(diagram 2) 

Use the drain collar #5 by itself; remove the 

rubber seal, nut and gaskets from the drain assembly. 

(diagram 3, next page)

 Push the drain collar #5 into the drain hole between the pan and the 2” pipe.  

With the drain collar pushed flush to the pan surface, the 2” drain pipe should not extend past the inside threads of the drain collar #5.

diagram 2

11” for shampoo shelf

minimum gap

required for

shampoo shelf

11”

triple studs

3/4” overhang when using triple studs, no overhang when using double studs

(double studs required, triple studs recommended for extra-strength)

1/4” cement board

2 x 4 stud

metal flange

pan

diagram 1

floor of pan

silicone bead

Содержание Sistine Stone Single Alcove-Hsf

Страница 1: ...ower Installation time may vary depending on your experience complexity of shower and Pre Installation Preparation Work which may include plumbing relocation drain location and bathroom demolition Pri...

Страница 2: ...LAR SAW BRACES TO SECURE WALL PANELS SILICONE FOR CAULKING GUN See silicone recommendations Page 7 2 CHECK YOUR SHIPMENT AGAINST APPROPRIATE PACKING LIST Make sure you have received all the items nece...

Страница 3: ...y screwing in the 1 4 cement board the metal flange will pull fast to the studs and will secure the metal pan in place diagram 1 With the pan in position check to make sure the 2 drain pipe is in the...

Страница 4: ...drain collar pan 6 rubber gasket 7 teflon slide ring 8 drain lock nut apply silicone around drain collar sides and under lip floor hole with 2 drain pipe diagram 3 1 Remove the shower pan to a safe l...

Страница 5: ...If the seams of the cement board are not flush and square your wall panels will not be square and flush 2 Place the cement board against the studs and rest it on the top of the shower pan back flange...

Страница 6: ...osition diagram 7 Rest 2B panel onto the pan floor use spacers between the floor and the panel to make the top of the panel level 2 Place the second bottom panel 1B into position push the two panels t...

Страница 7: ...roper amount you will need for the project based on your shower size Depending on the size and threshold type of your shower you will need from 10 20 9 8 oz tubes of silicone to complete your shower i...

Страница 8: ...ush with the inside of the shower pan threshold diagram 15 Make sure to align the glass channels in the thresholds with the glass channels in the shower pan if glass unit 4 Place the remaining trim pi...

Страница 9: ...from the bolt 5 Start with the top hole on the glass door Place the long bolt through the hole in the door keeping the remaining rubber pieces on the bolt On the other side of the glass place the flat...

Страница 10: ...nto the studs behind the decorative stone threshold 4 Re align the door and install screws in hinges 5 Install the door sweep onto the bottom of the door with the water flap facing the inside of the s...

Страница 11: ...Medium Sistine Stone use Linen Product No 15303 2 Follow the grout directions for specific application instructions a water based non sanded grout is recommended 3 If you desire a powdered grout use...

Страница 12: ...13395 Estelle Street Corona California 92879 Phone 800 454 2284 Fax 951 734 1480 Visit us at www americanbathfactory com NOTES...

Отзывы: