WALL PANEL/LINER INSTALLATION (continued)

TIME REQUIRED

3-4 HR

10

 

C - Installing Panels 
 

8.  Sand the backside surface of the wall panels with 60 grit sandpaper. This will increase the bond  

    to the silicone. Remove all dust and dirt with a clean dry cloth.
 9.  Start with panel 2B, apply a generous amount of silicone to the cement board and to the back  

    side of the wall panel. Refer to “Silicone Recommendations” on previous page for applying  

    silicone. Also refer to the manufacturer’s recommendations for application and drying time.

10.  Press the wall firmly into position. Be sure to use spacers between the bottom panel and the  

    shower pan to ensure panel is level. 

(diagram 12)

 11.  Install the remaining panels in the following order: 1B, 2L, 1L, 2T, 1T, 1LT & 2LT.  

    Match the space between the panels with the rest of the grout lines on the panel.  

    Use spacers if necessary to make the walls square and straight.

THRESHOLD TRIM

TIME REQUIRED

1/2 - 1 HR

11

8

 The threshold trim pieces complete the look of your new shower system. If you purchased a Basic 

Package which does not come with glass, your threshold pieces will be solid, without a channel. If 

you purchased a Supreme Package which comes with glass, the threshold pieces will have a channel 

for the glass panels. No matter what package you ordered there are 2 special cap trim pieces and 2 

special notched bottom left and right pieces.
1.   Locate all the trim pieces and align them on the floor. 

(diagram 13)

 2.  Apply silicone, using a zig-zag pattern, to the cement board along the panel’s edge, approximately  

    4 inches out: to the far outside of the shower pan. 

(diagram 14)

    Do not install the small cap trim pieces if your package includes glass. These trim pieces are to be  

  installed after the glass and door have been installed. If you did not purchase a package  

    with glass, you can install the cap trim pieces as outlined in step 4 below.

3.   Starting with the special bottom threshold piece, place the threshold into position making sure to  

    align the threshold with the vertical plumb line previously drawn on the cement  

 

    board. Apply pressure to the trim piece to bond it to the cement board. The trim piece should be  

    flush with the inside of the shower pan threshold. 

(diagram 15) 

Make sure to align the glass  

    channels in the thresholds with the glass channels in the shower pan. (if glass unit)

4.   Place the remaining trim pieces into position. Make sure to use a level and the plumb line  

    previously drawn on the cement board to align the trim pieces vertically.

Wall thresholds should be flush on the inside and

outside of the pan

See manufacturer’s recommendations for drying time

cap trim pieces

TLC 

TRC 

TLT 

TRT 

TLB 

TRB 

diagram 13

special notched bottom pieces

diagram 14

diagram 15

B races may be required to keep walls flush

cement 

board

diagram 12

1B

2B

2T

2L

1L

2LT

Содержание Sistine Stone Double Corner-Hdm

Страница 1: ...tallation Preparation Work which may include plumbing relocation drain location and bathroom demolition Prior to demolition scheduling a contractor or building your shower double check that you have a...

Страница 2: ...BRACES TO SECURE WALL PANELS SILICONE FOR CAULKING GUN See silicone recommendations Page 7 2 CHECK YOUR SHIPMENT AGAINST APPROPRIATE PACKING LIST Make sure you have received all the items necessary fo...

Страница 3: ...crewing in the 1 4 cement board the metal flange will pull fast to the studs and will secure the metal pan in place diagram 1 With the pan in position check to make sure the 2 drain pipe is in the cen...

Страница 4: ...drain collar pan 6 rubber gasket 7 teflon slide ring 8 drain lock nut apply silicone around drain collar sides and under lip floor hole with 2 drain pipe diagram 3 1 Remove the shower pan to a safe l...

Страница 5: ...efore installing the cement board To do this staple plastic so that it hangs 1 above the floor Roofing nails may be used to attach the cement board instead of screws this prevents the plastic from wra...

Страница 6: ...s have been stored improperly or seemingly have become extensively bowed they can be easily flattened before installation See troubleshooting section on last page for details B Test Alignment by Dry f...

Страница 7: ...proper amount you will need for the project based on your shower size Depending on the size and threshold type of your shower you will need from 10 20 9 8 oz tubes of silicone to complete your shower...

Страница 8: ...ial cap trim pieces and 2 special notched bottom left and right pieces 1 Locate all the trim pieces and align them on the floor diagram 13 2 Apply silicone using a zig zag pattern to the cement board...

Страница 9: ...ear washers from the bolt 5 Start with the top hole on the glass door Place the long bolt through the hole in the door keeping the remaining rubber pieces on the bolt On the other side of the glass pl...

Страница 10: ...g the inside of the shower Adjust the door sweep so there is enough friction between the door threshold and the rubber flaps to keep the door secure when closed but not too tight as to make the door d...

Страница 11: ...Medium Sistine Stone use Linen Product No 15303 2 Follow the grout directions for specific application instructions a water based non sanded grout is recommended 3 If you desire a powdered grout use...

Страница 12: ...NOTES 13395 Estelle Street Corona California 92879 Phone 800 454 2284 Fax 951 734 1480 Visit us at www americanbathfactory com G_00802 Rev B...

Отзывы: