9400016-J0 Rev D
9.0
12.3
6.0 TYP
5.25
4.03
5.25 TYP
21.0
24.3
28.1
16.0
Figure 17 — Rack Mounting Details (top view), Welded Rack
6.5 Power System Assembly and Mounting
The power system must be mounted in a clean and dry environment. Sufficient free space must be provided at the
front and rear of the power system. This is to meet the cooling requirements of the rectifiers and to allow easy ac-
cess to the power system components.
6.5.1 Floor Mounted Systems
Secure the system to a concrete floor using either heavy duty anchors (½" x 2½"), or for wooden floors, heavy-duty
lag screws (5/8" x 2½"). Use appropriately sized flat washers.
If required, use isolation kits to isolate system from the floor.
Secure the relay rack to the overhead cable tray. Alpha does not supply the mechanical details necessary for over-
head support.
The CXPS-E3 power system requires at least 2RU (3.5") of space above the distribution
for tooling access to the load breaker ground connections. Ensure that at least 2RU of
space is open in the relay rack above the E3 distribution.
NOTE:
Weight and Dimensions
The weight of the system with no rectifiers or converters installed is approximately 650lb or 295kg. The weight of the
systems given below are approximate and exclude rectifiers:
System
Total Weight (lb)
Total Weight (kg)
CXPS-E3 19" Systems e/w 48-2.4kW shelves
37.6
17.1
CXPS-E3 23" Systems e/w 2 x 48-2.4kW shelves
58.0
26.4
Refer to drawing 0250020-06 at the rear of this manual for system dimensions.
Dimensions in Figure 17 and Figure 18 are in inches.