Condensate Piping
This unit is designed for either right or left side exit of
condensate piping in downflow applications. Refer to
Figure 45 for condensate trap locations.
NOTE:
If necessary the condensate trap may be installed
up to 5” away using PVC pipe from the furnace. Piping
from furnace must slope down a minimum of 1/4” per ft.
toward trap.
1. Determine which side condensate piping will exit the
unit, location of trap, field-provided fittings and length
of PVC pipe required to reach available drain.
2. Use a large flat head screw driver or a 1/2” drive
socket extension and remove plug (Figure 45) from
the cold end header box at the appropriate location
on the side of the unit. Install provided 3/4 NPT street
elbow fitting into cold end header box. Use Teflon tape
or appropriate pipe dope.
3. Install the cap over the clean out opening at the base
of the trap. Secure with clamp. See Figure 50.
4. Install drain trap using appropriate PVC fittings, glue
all joints. Glue the provided drain trap as shown in
Figure 50. Route the condensate line to an open drain.
Condensate line must maintain a 1/4” downward slope
from the furnace to the drain.
5.
If unit will be started immediately upon completion of
installation, prime trap per procedure outlined in Unit
Start-Up section.
Do Not
use copper tubing or existing copper condensate
lines for drain line.
CAUTION
Figure 45. Condensate Trap and Plug Locations
Condensate line must slope downward away from the
trap to drain. If drain level is above condensate trap,
condensate pump must be used. Condensate drain line
should be routed within the conditioned space to avoid
freezing of condensate and blockage of drain line. If
this is not possible, a heat cable kit may be used on the
condensate trap and line. Heating cable kit is available in
various lengths:
6 ft. (1.8 m) - kit no. 26K68; 24 ft. (7.3 m) - kit no. 26K69;
and 50 ft. (15.2 m) - kit no. 26K70.
Figure 46. Condensate Trap Location
(shown with right side exit of condensation)
Содержание 96G1DFE
Страница 30: ...507769 04 Page 30 of 53 Issue 1927 Figure 50 Trap Drain Assembly Using 1 2 PVC or 3 4 PVC ...
Страница 36: ...507769 04 Page 36 of 53 Issue 1927 Figure 57 Typical Wiring Diagram ...
Страница 48: ...507769 04 Page 48 of 53 Issue 1927 Troubleshooting Heating Sequence of Operation ...
Страница 49: ...507769 04 Page 49 of 53 Issue 1927 Troubleshooting Heating Sequence of Operation continued ...
Страница 50: ...507769 04 Page 50 of 53 Issue 1927 Troubleshooting Cooling Sequence of Operation ...
Страница 51: ...507769 04 Page 51 of 53 Issue 1927 Troubleshooting Continuous Fan Sequence of Operation ...