Installation
12
Verifying
Installation
1.
Establish a connection from the device connected to Port 1 to the device
connected to Port 2.
2. Once the connection between the devices that attach to 10Base-T Port
1 and Port 2 has been successfully established, remove the RJ-45
connector from Port 2 and connect it to the unit’s remaining 10Base-T
ports to verify functionality.
3. If all ports test successfully, install the remaining 10Base-T RJ-45
connections and make sure that the LINK LED for each port is lit.
Remember, the 10Base-T device on the opposite end of the UTP cable
must be operational.
The LINK LED validates the receive pair only. The opposite end of
the UTP segment is responsible for validating the transmit pair.