1A
OPERATIONS
1A-14
1.16 Drive Belts
To Replace
1. Remove screws from splash guard plate.
2. Remove belt from lower pulley, and then torque converter.
3. Loosen set screws(A) on both the u-joints where they couple to the drive shaft. (refer to fig. 2A)
4. Slide u-joint(B) to the right off the drive shaft to create a gap in the drive line to allow removal of
belt through gap. (refer to fig. 2B)
5. Install new belts through gap and reverse process to replace new belt.
Be sure to reset the gap
between the U-Joints to between 3/64 to 3/16
(C)
.
(refer to figure 2B)
6. Replace cover and replace all fasteners.
C
A
B
Refer to 2A-6 for parts breakdown
C
Figure 2A
Figure 2B
Содержание RAZORBACK RIDERS PRO1200C
Страница 1: ......
Страница 21: ...1A OPERATIONS 1 21 Engine Safety 1A 19...
Страница 22: ...1A OPERATIONS 1 21 Engine Safety cont d 1A 20 Adding Fuel in Gas Engines...
Страница 23: ...1A OPERATIONS 1A 21 1 21 Engine Safety cont d Adding Fuel in Diesel Engines...
Страница 29: ...2A PARTS DRIVELINE ASSEMBLY 2A 6 Modified 6 14 07...
Страница 33: ...2A PARTS 2A 10 SUPER HEAVY DUTY SHD GEARBOX LEFT HAND SITTING ON MACHINE SOM PART 046794...
Страница 34: ...2A PARTS 2A 11 SHD GEARBOX LEFT HAND SOM PART 046794 cont d...
Страница 35: ...2A PARTS 2A 12 SUPER HEAVY DUTY SHD GEARBOX RIGHT HAND SITTING ON MACHINE SOM PART 046795...
Страница 36: ...2A PARTS 2A 13 SHD GEARBOX RIGHT HAND SOM PART 046795 cont d...
Страница 39: ...2A PARTS OFFSET ALIGNMENT TUTORIAL 1 of 3 2A 18...
Страница 40: ...2A PARTS 2A 19 OFFSET ALIGNMENT TUTORIAL 2 of 3...
Страница 41: ...2A PARTS OFFSET ALIGNMENT TUTORIAL 3 of 3 2A 20...