4 Installation
4.1
Unpacking/delivery
The Alfa Laval Tote Blast Station will arrive on a skid with separate boxes for the pump, hose, and control panel.
All of the components in the system include:
-
Multistage centrifugal pump
-
Control panel
-
¾” × 50’ hose
-
Two 1-1/4” ANSI flanges
-
Two 1-1/4” gaskets
-
1-1/4” × ¾” reducer coupling
-
Eight flange bolts
-
Eight flange nuts
-
¾” 90 degree elbow
-
2” Tote insertion fabrication
Open the boxes and remove all of the components with the exception of the pump. The pump will be positioned lying down in
the crate and must be raised in an upright position. To raise upright, use some type of mechanical hoist (fork lift, crane, etc.) and
the J-hooks placed on the motor of the pump to gently raise it upright and remove from the box. In some cases eye bolts may
be needed to move the pump. The mechanical hoist must also be used to position the pump into place for mounting. Remove
the packaging from all of the components and make sure the correct number of each component is included.
If components are missing or excess components were shipped please contact Alfa Laval.
4.2
Tools and materials
Installation of the ToteBlast System requires a basic set of hand tools but Alfa Laval also recommends the following tools
and materials for the mounting of the pump:
-
Concrete hammer Drill with ½” bit
-
Four vibration-resistant wedge stud anchors (McMaster Carr part # 94475A263) or equivalent
For all electrical work including the mounting, positions, and wiring of all system components, Alfa Laval recommends hiring a
professional electrician and installing everything according to industry standards.