5/ PUMP START UP
5.1 - PREPARATIONS
a. Connect the electrical motor in accordance with the local rules and regulations. Perform this workby
qualified personnel.
b. Undertake rollar ajustment of the pump according to the pump process (see §6.3 ROLLAR AJUST-
MENT).The pumps are always delivered with non-ajusted rollars.
c. Check the direction of rotation of the pump. It is recommended to install a rotation inverter on the
motor for the hose change.
5.2 - START UP
a. Install piping at the inlet and outlet of the pump.
b. Make sure that valves at the inlet and outlet are opened.
c. Start the pump by checking its direction of rotation by the sight glass.
d.Check the flow and discharge pressure and ajust rollars if these figures don’t match the pump speci-
fications.
4.5 - LIFTING THE PUMP
Pumps are provided with two lift holes placed on the upper part of the frame.
While lifting the pump, respect the following points :
- Lift the complete hose pump using the lifting holes plus additional support on the gearbox and the
motor using suitably rated straps or slings.
- Never exceed the upper limits of lift and control the motorized pump weights in the table below.
- The motorized pump, given its centre of gravity, will tend to overbalance on the pump head side.
Make sure that the persons are at a security distance of the pump to avoid any risk of wound.
- Never raise the pump otherwise than by the pump’s lifting rings.
- Never raise the pump by it’s orifices.
ALL WEIGHTS IN KILOGRAMS
PART
ALP09
ALP13
ALP17
ALP25
ALP30
ALP45
FIXED
SPEED
8
9
15
36
80
127
VARIABLE
SPEED
12
13
19
46
90
150
Lifting holes