Aircel AHLD E-Series Скачать руководство пользователя страница 14

14

Start-Up Procedure

At any point during the process of startup or shutdown, you notice anything unusual; we recommend you 

refer to the operation manual immediately. If you cannot find the answer in the troubleshooting section, 

contact your Aircel representative or the factory at once. 

1.  Ensure that the dryer is connected to a 

suitable compressed air supply. Make sure 

that the pressure of the supply is equal to 
the normal operating pressure of the dryer. 

2.  Check to make sure the “shut-off’ valves 

are closed and that by-pass valve is open. 

3.  Close all manual drain/vent valves. 

4.  Slowly pressurize the dryer by gradually 

(slowly) opening the inlet shut-off valve to 
the OPEN position. 

5.  When both towers of the dryer are 

completely pressurized, check the complete 
system for possible air leaks. Use soap 

and water to test all joints and fittings. 

If any leaks are detected, immediately 
depressurize the unit and correct the leaks.

6.  Make certain that any automatic 

condensate drain isolation valves are in 
the open position so proper condensate 
draining can occur. 

7.  When normal operating pressure is 

reached, switch on electrical power (Turn 
switch to ON position) 

8.  With by-pass valve closed, open the outlet 

valve slowly to allow air downstream. 

9.  When energized one of the towers should 

depressurize. 

10. Check the operation of several cycles 

completely by following the control panel 
display screen operation, the panel lights 

on the electrical box, and the tower 
pressure gauges to make certain the dryer 

system is operating as displayed. Also 

refer to the how it works section, flow 

diagram, electrical drawing, dryer control 
display screen descriptions, and sequence of 
operation in this manual for reference.

11. Check the drain valve for proper operation 

and discharge of liquid (filters and 
separators, etc.). 

12. Near the dryer outlet (APV) valve, check 

the control air/ pilot air regulator secondary 
pressure, the regulator gauge should read 

100 psig. Increase or decrease regulator 
knob to achieve a 100 psig control air 

secondary pressure reading. 

13. Make certain the purge exhaust valves 

slowly open within an 8 to 12 second time 

period, some adjustment of the flow control 
valve attached to the actuator may be 
required, after adjustment tighten down the 

locking collar.

14. Make certain a slight amount of air flow 

is felt at the end of the EMS RH sensor 
sample cell exhaust coil tube (this is 
normally located at the back of the dryer) 

adjust the needle valve to give more or less 
flow.

15. Review the dryer system display screen 

shots (in this manual) to make certain 

the parameters are set as needed in the 
customer dryer. 

16. Purge air flow is preset and not adjustable.

After the initial startup, the dryer operation is completely automatic. To understand the details of the 

operation, we recommend you use the how it works section, flow diagram, electrical drawing, dryer control 

display screen descriptions, and sequence of operation in this manual for reference. 

Aircel AHLD E-Series - Models 70 - 750

Содержание AHLD E-Series

Страница 1: ...ION indicates a potentially hazardous situation which if not avoided may result in minor or moderate injury Notice used to address practices not related to personal injury This manual is property of t...

Страница 2: ...e system before performing maintenance or service work DO NOT operate the equipment with the control panel door open Notice For optimum performance use only Aircel replacement parts This manual contai...

Страница 3: ...t to make changes without any prior notification and is not obligated in any manner Information in this manual is deemed current at the time of publication and Aircel disclaims all liability for any e...

Страница 4: ..._ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ Dryer Desiccant Weight per Vessel _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _...

Страница 5: ...shock and only authorized personnel with proper gear must approach it High Noise Area All personnel are required to wear ear protectors before approaching the vicinity of the equipment Hazardous Fume...

Страница 6: ...tive equipment used on the machine Safe Operating Procedures 1 Pressurize and depressurize compressed air SLOWLY Always open air valves slowly when pressurizing the airline system or equipment Replace...

Страница 7: ...ection rates are reduced Purpose Intended Use Aircel Regenerative Desiccant Air Dryers can dry compressed air to 100 F PDP Pressure Dew Point Standard Regenerative Desiccant Air Dryers dry compressed...

Страница 8: ...design failure of power and or pilot air causes the purge exhaust valves to close eliminating loss of air pressure The System also provides uninterrupted drying air flow preventing a deadheading affec...

Страница 9: ...substantiate the claim 5 File claims with the delivery carrier 6 Compare unit received with description of product ordered Check the serial plate label and make sure that it is the correct Model was...

Страница 10: ...enerating tower T2 through exhaust valve V4 and exhaust muffler to ambient After regeneration cycle is complete valve V4 closes causing tower T2 to repressurize to line pressure Next the towers will s...

Страница 11: ...Regenerating Tower Air Saturated with Moisture Dry Air F1 F2 T2 T1 V1 V2 F1 Mounted Pre Filter F2 Mounted After Filter V1 Automatic Piston Valve V2 Automatic Piston Valve V3 Purge Exhaust Valve V4 Pur...

Страница 12: ...ttached piping Location Careful consideration should be given to the location of the dryer in order to assure optimum results Ensure that the load bearing weight of the floor is adequate for the weigh...

Страница 13: ...taken when filling the media and it must be done gradually to prevent powdering Muffler If the event that mufflers have been shipped loose they must be installed and secured By pass If the dryer is no...

Страница 14: ...en operation the panel lights on the electrical box and the tower pressure gauges to make certain the dryer system is operating as displayed Also refer to the how it works section flow diagram electri...

Страница 15: ...y depressurizing vessel 2 T2 Simultaneously the inlet and outlet APV Automatic Piston Valve V1 V2 shift positions directing the inlet air to vessel 1 T1 to be drying the air The air flows up through t...

Страница 16: ...T1 will be regenerating vessel 1 T1 purge exhaust valve V3 is still open vessel 2 T2 is drying the inlet air A small portion of dry outlet air from vessel 2 15 average based on standard design capaci...

Страница 17: ...essure in the regenerating tower change mufflers on a regular basis typically every 2 3 months for optimum performance D Oil and oil vapor can drastically reduce the life of the desiccant Take precaut...

Страница 18: ...lly every 2 3 months for optimum performance 4 Check desiccant condition Powder in the mufflers is a indication of the status of the desiccant 5 Check all solenoid valves coil condition and control ci...

Страница 19: ...d powered down Follow the shut down procedures Note Some troubleshooting will have to be done while system is pressurized and energized so use extreme caution 1 Depressurize the unit 2 Check to make s...

Страница 20: ...properly should be adjusted so exhaust valve opens within a 8 12 second time period APV valve leaking Dismantle and clean replace seals and piston if needed No input power Check that dryer is on with...

Страница 21: ...clean and reinstall Outlet APV valve malfunction Dismantle clean and reinstall Purge Failure Purge muffler clogged Remove and clean replace if needed Purge flow orifice in the outlet APV valve may be...

Страница 22: ...ields Wear chemical resistant protective gloves Wear protective clothing Eye wash fountains and safety showers must be easily accessible Potential health effects Primary routes of exposure Routes of e...

Страница 23: ...ust ACGIH TWA value 1 mg m3 Respirable fraction Safety data sheet F200 Revision date 2008 12 04 Version 3 0 Page 2 5 30286124 MDS_GEN_US EN If on skin After contact with skin wash immediately with ple...

Страница 24: ...ical and chemical properties Safety data sheet F200 Revision date 2008 12 04 Version 3 0 Page 3 5 30286124 MDS_GEN_US EN Form Odour Colour pH value Melting point Boiling point Vapour pressure Density...

Страница 25: ...ments are dependent on the hazard classification and will vary by location and the type of disposal selected All waste materials should be reviewed to determine the applicable hazards testing may be n...

Страница 26: ...DATA OR INFORMATION MAY BE USED WITHOUT INFRINGING THE INTELLECTUAL PROPERTY RIGHTS OF OTHERS IN NO CASE SHALL THE DESCRIPTIONS INFORMATION DATA OR DESIGNS PROVIDED BE CONSIDERED A PART OF OUR TERMS...

Страница 27: ...Air Dryer Aircel Programmable Controller Text Display DEL Key ESC Key Left Arrow Key Down Arrow Key On Key Key Right Arrow Key Up Arrow Key ALT Key Red LED Common alarm light Standard alarms EMS Humid...

Страница 28: ...croll to the alarm screen to view the alarms press the left arrow once from the main screen to view the alarm screen Step 3 Vessel 2 Repressurizing 241 300 secs Vessel 2 T2 purge exhaust pilot solenoi...

Страница 29: ...purge exhaust valve V3 to close this allows vessel 1 T1 to repressurize to line pressure since air continues flowing though the small orifice in the outlet APV valve V2 pressurizing vessel 1 T1 Step...

Страница 30: ...cel Programmable Controller Main Screen Navigation LEFT RIGHT LEFT RIGHT ALARM SCREEN CONTROL MENU Control Menu Navigation LEFT RIGHT LEFT RIGHT MAIN SCREEN SETTINGS MENU Aircel AHLD E Series Models 7...

Страница 31: ...h OK to engage the menu Scroll to the desired selection and Push OK SETTINGS SCREEN To engage Push OK then scroll to the desired set point to be changed Push OK on the set point to be changed and use...

Страница 32: ...e cycle for lower dewpoint option Time Control Menu Operation LEFT RIGHT LEFT RIGHT TIME CYCLE CONTROL SETTINGS MENU ANALOG SCREEN TIME CONTROL MENU To change the time cycle Push OK then scroll to the...

Страница 33: ...ntroller Analog Screen Navigation The analog screen simply displays the analog output signals Hours of Operation Screen Navigation The hours of operation screen gives the user the amount of run time a...

Страница 34: ...ched set point check desiccant prefilters control system Failure to Shift option tower did not properly repressurize Bad Probe the EMS sensor has reached an out of range signal check sensor and cable...

Страница 35: ...of range When this happens the signal has either been lost or the sensor may need to be replaced The Bad DEW P Probe is the alarm for the dew point sensor probe out of range The out of range can be e...

Страница 36: ...36 Electrical Drawings Main Power PLC Input All AHLD E Models Aircel AHLD E Series Models 70 750...

Страница 37: ...Heatless Regenerative Desiccant Air Dryer 37 Electrical Drawings Main Power PLC Input All AHLD E Models...

Страница 38: ...38 Electrical Drawings PLC Output Sensors All AHLD E Models Aircel AHLD E Series Models 70 750...

Страница 39: ...Heatless Regenerative Desiccant Air Dryer 39 Electrical Drawings PLC Output Sensors All AHLD E Models...

Страница 40: ...40 Electrical Drawings Back Panel All AHLD E Models Aircel AHLD E Series Models 70 750...

Страница 41: ...Heatless Regenerative Desiccant Air Dryer 41 Electrical Drawings Enclosure Layout All AHLD E Models...

Страница 42: ...42 Service Notes Date Service Performed Notes Aircel AHLD E Series Models 70 750...

Страница 43: ...Service Notes Date Service Performed Notes Heatless Regenerative Desiccant Air Dryer 43...

Страница 44: ...orrosion lack of proper maintenance incorrect installation modification or misapplication of equipment Routine maintenance or adjustment required under normal operation as outlined in the Aircel opera...