background image

Maintenance&Trouble Shooting 

22

Storage device fault

low start up power under low light 

conditons, inverter self-check procedure 

cannot be complete

The  inverter will restart automatically when the start up power is enough

Ground Fault Circuit Interrupter 

fault

1.ground leakage current high

2.PV(+) or PV(-)  earthed

1. check the AC output wring and restart the inverter

2. check PV array wiring

Grid Frequency fault

1. grid fluctuate

2. grid frequency out of setting range

1. grid back to the normal, the inverter will restart automatically

2. check inverter frequency setting range correct

3. check the AC output wiring well connected

Grid voltage fault

1. grid fluctuate

2. grid voltage unbalance between phase 

to phase

1. grid back to the normal, the inverter will restart automatically

2. check each phase's voltage via inverter LCD

Internal fault B

Bus voltage out of range

1. check PV input voltage (not bigger than

 

900Vdc per channel)

2. check the AC output wiring well connected

Internal fault D

Software over current fault

1. check PV array confirguration is correct

2. fluctuate on grid, wait for the grid back to the normal, the inverter

 

will

 

restart

 

automatically

Error Display

Error Message

Possible Fault

Correctie Measure

EepromErr

GFCI.Err

GridF.OutLim

GridV.OutLim

IntFaultB

IntFaultD

Trouble-Shooting List 

Internal fault E

Over current fault

grid back to the normal, the inverter will restart automatically

Internal fault G

DCI high

1.check each PV array's confirguration is correct

2.check the voltage difference between BUS+ and BUS- is too high

Internal fault K

Bus voltage fault

1.check the AC output wring well connect.Use stranded copper cable

2.check PV array confirguration is correct

3.check the voltage difference between BUS+ and BUS- is too high

IntFaultE

IntFaultG

IntFaultK

Internal fault M

Bus voltage fault

1.check the AC output wring well connect.Use stranded copper cable

2.check PV array confirguration is correct

3.check the voltage difference between BUS+ and BUS- is too high

IntFaultM

Internal fault N

Hardware fault

check the AC out put wring well connect.Use stranded copper 

cable

IntFaultN

Internal protection A

Bias current protection

1. turn off AC, then DC circuit breaker, restart the inverter

2. replace the control board

IntProtectA

Internal protection B

Relay fault

turn off AC, then DC circuit breaker, restart the inverter

IntProtectB

Internal protection C

Inverter current protection

turn  off  AC,  then  DC  circuit  breaker,  restart  the  inverter,  check  the 

each

 

phases'

 

AC

 

voltage

 

is

 

correct

 

through

 

LCD

IntProtectC

Internal protection D

Boost current protection

turn off AC, then DC circuit breaker, restart the inverter

IntProtectD

Internal protection G

Bus voltage protection

1.check the AC output wring well connect.Use stranded copper cable

2.check PV array confirguration is correct

3.check the voltage difference between BUS+ and BUS- is too 

IntProtectG

high

Internal protection I

Bus voltage protection

1.check the AC output wring well connect.Use stranded copper cable

2.check PV array confirguration is correct

3.check the voltage difference between BUS+ and BUS- is too high

IntProtectI

Internal protection K

Bus over voltage protection

check the AC output wring well connect.Use stranded copper cable

IntProtectK

Internal protection N

Inverter over current protection

fluctuate on grid, wait for the grid back to the normal, the inverter will 

restart automatically

IntProtectN

Internal protection P

Frequency fault protection

frequency abnormal of grid, wait for the grid back to the normal, the 

inverter will

 

restart

 

automatically

IntProtectP

Internal protection Q

DCI protection

1.check PV array confirguration is correct

2.check the voltage difference between BUS+ and BUS- is too high

IntProtectQ

Internal protection R

DCI circuit protection

1. turn off AC, then DC

IntProtectR

 circuit breaker, restart the inverter

2. replace the control board

IntProtectT

Internal protection T

PV over current protection

turn off AC, then DC circuit breaker, restart the inverter

IsolationErr

Insulation resistance fault

Insulation resistance low

check the resistance between PV(+) and ground, PV(-) and 

ground bigger than 2M

Ω

.

PVVoltOver

PV voltage high

PV over voltage

check PV array confirguration is correct

  

SPICommErr

SPI fault

SPI communication fault

check the RS485 cable is well connect

TempOver

Over temperature

Over temperature

1. turn off the inverter still the temperature down to the normal. Or

install

 

the inverter

 

at

 

a

 

well

 

ventilated

 

site.

2. check the heat sink and the fans is working

TempSensorErr

Temperature sensor fault

Temperature sensor fault

1. turn off AC, then DC circuit breaker, restart the inverter

2. replace the temperature sensor

Содержание Anybuild BNT012KTL

Страница 1: ...Installation and Operation Manual On Grid PV Inverter ...

Страница 2: ...ction 3 5 1 PV Connection 3 5 2 Grid Connection 3 5 3 Earth Connection 3 5 4 Communication Connection WIFI Ethernet GPRS RS485 4 Operation 4 1 Control Panel 4 2 Menu Structure 4 3 Setting 4 3 1 Startup Setting 4 3 2 Parameter Setting 4 3 3 Query Interface 5 Commissioning 6 Shut Down Restart the Inverter 6 1 Shut Down Procedures 6 2 Restart the inverter 7 Maintenance Trouble Shooting 7 1 Maintenanc...

Страница 3: ...TL BNT010KTL BNT012KTL BNT013KTL BNT015KTL BNT017KTL BNT020KTL Please keep this manual all the time available in case of emergency About This Manual 01 The typical connection diagram for the entire PV system is on grid Circuit Breaker Circuit Breaker 1 Surge Protective Device DCA1 DCA1 PE N L 3 PV Inverter PVA1 AC Grid Circuit Breaker 2 Surge Protective Device Surge Protective Device DCA2 DCA2 PVA...

Страница 4: ... 3 7 8 5 10 5 13 5 16 16 16 16 25 Type Max AC Current A Rate current of AC breaker A BNT010KTL BNT012KTL BNT013KTL BNT015KTL BNT017KTL BNT020KTL 17 21 5 22 27 30 32 25 32 32 32 40 40 Circuit Breaker and Surge Protector Recommendation SPD Lightning protection system refer to the following options AC side nominal discharge current 20KA second grade lightning protection protection voltage 2 5KV DC si...

Страница 5: ...enance Safety Symbols 03 2 2 Explanations of Symbols Danger of Electric Shock The inverter contains fatal DC and AC power All work on the inverter must be carried out by qualified personnel only Beware of hot surface The inverter s housing may reach uncomfortably hot 60 C 140 F under high power operation Do not touch the inverter enclosure when operation Residual power discharge Do not open the in...

Страница 6: ...s 4 pairs Instruction 04 No 1 2 3 4 5 6 7 8 1 1 1 1 1 1 1 3 Solar Inverter Certificate Of Inspection Quick Installation Instructions Warranty Card Wall Mounting Bracket Grounding Terminal Zero Injection Connector Optional Plastic Expansion Tube 9 10 11 12 13 14 15 16 3 1 1 2 3 4 4 1 1 4 Mounting Bracket Screw Security Screw Screwdriver For Security Screw DC Connector sets AC Wiring Cover Screw AC ...

Страница 7: ...Installation 05 3 2 Product Overview BNT012 015KTL 345mm 680mm 170mm 170mm BNT003 006KTL 345mm 400mm BNT008 010KTL 345mm 460mm BNT017 020KTL 345mm 680mm ...

Страница 8: ...erview of the Connection Area The following figures show the assignment of the individual connection areas on the bottom of the inverter Installation 06 BNT003 010KTL 4 1 2 3 6 BNT012 015KTL 4 1 2 5 3 5 6 ...

Страница 9: ...aterials where is suitable for inverter s weight and dimensions The ambient temperature should be within 25 60 between 13 F and 140 F The installation of inverter should be protected under shelter Do not expose the inverter to direct sunlight water rain snow spray lightning etc Installation 07 3 3 Mounting Location No 1 2 3 4 5 6 DC Switch DC Connectors For PV Strings DC Connectors For PV Strings ...

Страница 10: ...led vertically on the wall or lean back on plane with a limited tilted angle Please refer to below picture Leave the enough space around inverter easy for accessing to the inverter connection points and maintenance 30 0 300mm 100mm 100mm 500mm Max ...

Страница 11: ...Installation 09 3 4 Installation On grid PV Inverter 328 5mm 26mm 26mm 35mm Step 1 Step 2 Step 3 Security screw ...

Страница 12: ...om PV strings are correct Use the DC plugs in the accessory The lightning protector should be equipped between PV strings and inverter Disconnect all of the PV DC switch during wiring 3 5 1 PV Connection Warning The fatal high voltage may on the DC side please comply with electric safety when connecting Please make sure the correct polarity of the cable connected with inverter otherwise inverter c...

Страница 13: ...ke sure below requirements are followed before connecting AC cable to the inverter Installation 11 3 5 2 Grid Connection MC STOP MC MC STOP MC Note You ll hear click sound when the connector assembly is correct Step 3 Note It is strongly recommended that BNT003 010KTL be connected to 2 strings of panels BNT012 015KTL to 3 strings of panels and BNT012 015KTL to 4 strings of panels ...

Страница 14: ...stallation 12 Warning The fatal high voltage may on the AC side please comply with electric safety when connecting Please make sure the right line of AC grid connected with inverter otherwise inverter could be damaged Note Please use PV connector crimper to pinch the point of the arrow Unscrew the row of screws insert the wire harness into the N W V U caps one by one and tighten the screws N Neutr...

Страница 15: ...ective earth PE terminal at the side of the inverter And make sure this PE terminal is reliable grounding Installation 13 3 5 3 Earth Connection Step 3 Fix junction box with screw Step 1 3 5 mm Grounding terminal Note copper cable or aluminum cable more than 6mm 4x ...

Страница 16: ...odule could transmit the data to the cloud server and display the data on the PC tablet and smart phone Wi Fi GPRS RS485 communication is applicable to the inverter Please refer to Communication Configuration Instruction for detailed instruction Install the Wi Fi GPRS RS485 Communication 3 5 4 Communication Connection Fasten Step 1 Step 2 ...

Страница 17: ...art Meter is used for monitoring the power consumption of home electricity the inverter will active export power limit function based on the monitoring data Please refer to Zero injection Smart Meter Instruction for detailed instruction 1 2 3 8 PIN Assignment RS485 A PIN 24 RS485B PIN 25 Zero Injection Port pin assignment 12345678 RJ45 Plug ...

Страница 18: ...ton UP Touch Button DOWN Touch Button ENT Touch Button POWER LED Indicator Grid Load PV Inverter PV Inverter PV Inverter Distribu on Cabinet L1 L1 L2 L3 L2 L3 PV Array RS485 WiFi Ethernet GPRS Afore Smart Meter PV Array PV Array Router Cloud Server Weather Sta on Energy Meter Note The Inverter could be connected in parallel with Smart Meter make sure the total load power not exceed Smart Mater s l...

Страница 19: ... OFF Power Factor GridPowerCtrl CTRL OFF ON POWER 3000 0 KWH Date Time Date Dd Mm 2020 Time Hh Mm Ss Clear Record Clear Err Record Clear Run Record Pdet xx RComp xx SET Para View Vac Max xx V Vac Min xx V Fac Max xx Hz Fac Min xx Hz Risomin xx Ko DCI Max xx ma TembientMax xx C TmoduleMax xx C OffDiffMax xx VacUnba xx Safty xxx EnergyK 105 00 Error Record No Error PV Limit PV A xx PV B xx Active Is...

Страница 20: ...rial number and firmware version of inverter check the error list of inverter including date and time Display the WIFI serial number and assigned IP address Displays the error records of inverter Set date and time of the inverter Enable or disable Zero injection function Set safety standard Set grid frequency protection range Set the protection parameters of inverter Error record WiFi Info Error R...

Страница 21: ...ter parameters by selecting SET Passwords are needed for the setting which only can be operated by after sales personnel to make sure the safety and normal operation of the inverter PV power limit PVA PVB PVA PVB 1 In fact only choose to adjust the PVA PVB is linked Only for three phase 3 10kW Note The inverter need to be restarted to finish parameter setting The open circuit voltage of each solar...

Страница 22: ...ordingly to local standards or regulations Commissioning Procedures Turn on the AC switch between inverter output and the public grid Turn on the DC switch on the inverter Turn on the PV switch of the system 5 Commissioning DOWN ENT UP ESC POWER FAULT COM FAULT Red LED Green LED Green LED POWER COM LED Indication Sign Color Explanation COM Green On Off On Off On Off Green Red FAULT Inverter is fee...

Страница 23: ...r output and the public grid Follow the procedures below when the inverter needs to be restarted Follow the Shut Down Procedures of Article 6 to shut down inverter Follow the Commissioning Procedures of Article 5 to turn on the inverter Shut Down Restart the Inverter 21 7 Maintenance Trouble Shooting 6 Shut Down Restart the Inverter 6 1 Shut Down Procedures 7 1 Maintenance 6 2 Restart the inverter...

Страница 24: ... control board IntProtectA Internal protection B Relay fault turn off AC then DC circuit breaker restart the inverter IntProtectB Internal protection C Inverter current protection turn off AC then DC circuit breaker restart the inverter check the each phases AC voltage is correct through LCD IntProtectC Internal protection D Boost current protection turn off AC then DC circuit breaker restart the ...

Страница 25: ...N50549 1 EN50438 RD 1699 UNE 217001 RD 413 IEC61727 IEC62116 IEC61683 VDE4105 UL1741 VDE0126 AS4777 2 NB T 32004 2013 PV Reverse Polarity Protec on PV Insula on Resistance Detec on AC Short Circuit Protec on AC Over Current Protec on AC Over Voltage Protec on An Islanding Protec on Residual Current Detec on Over Temperature Protec on Integrated DC switch Surge Protec on Dimensions W x H x D mm Wei...

Страница 26: ...dual Current Detec on Over Temperature Protec on Integrated DC switch Surge Protec on Dimensions W x H x D mm Weight kg Protec on Degree Enclosure Material Ambient Temperature Range Humidity Range Topology Communica on Interface Cooling Concept Noise Emission db Night Power Consump on W Max Opera on Al tude m EMC Standard Safety Standard Grid connec on 13200 12000 21 5 98 50 98 00 YES YES YES YES ...

Отзывы: