19
Fig. 5.e
5.a
Prepare the surface where the unit is to be mounted. Make sure that the surface is flat, leveled and that it supports the weight
of the unit. Perform the installation in accordance with local rules and regulations.
5.b
Use appropriate plugs and rods or screws (not supplied) to fix the unit to the ceiling. It is recommended to fit the unit with
anti-vibration mounts (not supplied).
5.c
Assure that the unit is completely flat once mounted to the ceiling, for the condensation drainage to function properly.
5.d
Connect the condensation elbow(s) to the drainage hole(s) on the access panel: in case close and seal the non-used hole
with the supplied plugs (2 plugs each hole). Make sure of water and air tightness of all connections. The condensation pipe
connection must be done in a way that makes easy to remove the access panel for the service operation. It is recommended
to use a U-bend (or similar) in the condensation drainage pipe.
5.e
Connect the unit to the duct system. Make sure that all necessary accessories are used to create a functional ventilation
solution.
Connect the unit electrically according to §5.4. Check that it starts up correctly.
Ø125
Ø125