NTX138 Installation Approval Test Procedure
Page 6 of 7
Aug 31, 2001
Rev. 1.00
E NG-FORM: 634-0100.DOT
CONFIDENTIAL AND PROPRIETARY TO NORTHERN AIRBORNE TECHNOLOGY LTD.
F.
Perform a coupled ILS approach to the aircraft's certified limits. Modulate the
NTX138 transmitter on the above frequencies for at least 20 seconds. Observe
any effect on the autopilot. Repeat for each different system such as ILS #2,
GPS, FMS etc.
Observations:
G.
List the power plant, fuel and other electric instruments in the chart provided and
note any anomalies that occur while transmitting. Assess the results.
STEP SYSTEM PASS
FAIL
NOTES
1
Xponder & Encoder
2
ADF 1 & 2
3 VG
4 Compass
5 Directional
Gyro
6 Oil
Pressure
7 Fuel
Pressure
8 Oil
Temp
9 Amps
10 Bus
Voltage
11 Fuel
%
12 Ng
13 TOT
14 Torque
%
15 Annunciators
16 Digital
Clock