background image

61287802F1-13F

5

f

     

CAUTION!

To reduce the risk of fire, use minimum no. 26 AWG

 telecommunications line cord.

Install the UPS 

Installation of the Uninterruptible Power Source (UPS) will be 
dictated by on-site conditions and local telephone company 
practices. Refer to the installation material that is provided with the 
UPS.

g

     NOTE

After the ground wire, fiber jumper, and power leads have been 
connected, close the ONT and secure it by tightening the inner 
security screw.

Power conductors, POTS, and Ethernet are suitable for 
connection to internal wiring or cabling only. Do not metallically 
connect these ports to interfaces that connect to external wiring. 
Do not connect this port to equipment located in other buildings 
or structures.

Installation of this product must comply with the National Electric 
Code (NEC). Final acceptance of this Listed equipment 
installation will ultimately be up to the local Authority Having 
Jurisdiction (AHJ).

This is to be installed by qualified service personnel only.

Connect Subscriber Services

For both POTS and Ethernet connections, refer to 

Figure 11

.

Connect POTS

To terminate the POTS lines, complete the following steps:

1. Route the subscriber POTS wires through the port (refer to 

Figure 11

).

Figure 11. Two Post Bridge and Installation Connections

RING

POTS1

POTS2

POTS3

POTS4

TIP

TELCO ACCESS

ETH 2

ETH 1

ETH 4

ETH 3

GPON 454 1287802F1

12V     , 1.25A

TELEPHONE TROUBLESHOOTING
1. Identify the bad line.
2. Disconnect the plug from the appropriate POTS jack and plug
    any working telephone into that jack.
      If the telephone works, there is a problem inside the house.
      If the telephone does not work, contact your service provider.
3. Remove the telephone and replace the plug into the POTS jack.
4. Close the unit.

This device is intended to be attached to a receiver that is not used to

receive over-the-air broadcast signals. Connection of this device in any

other fashion may cause harmful interference to radio communications

ans is in violation of the FCC Rules, part 15. 

CLEI

TEL. NUMBER

PWR

GPON

POTS1

POTS2

POTS3

POTS4

Ethernet Connections

POTS Connections

(Two Post Bridge)

Cable Routing Area

POTS and Ethernet

Port

Captive
Screw

2. Trim each wire to length. 
3. Connect the tip and ring wires to the terminal bridges.
4. Insert the RJ-11 connectors from the terminal bridges in the 

appropriate POTS Port.

Connect Ethernet to the ONT

1. Route the Subscriber Ethernet wires through the same cable 

entry as the POTS cables. 

2. Install RJ-45 connectors to the Ethernet wires.
3. Insert into the appropriate 

ENET 1–4 

socket.

4. Tie wrap both the POTS and Ethernet cables to the NID 

housing near the cable entry point point.

LED S

TATUS

The LED table below provides the LED status for the ONT.

R

EGISTRATION

 ID

There are two instances where the OLT will register the ONT:

Serial Number Activation (performed by the OLT when the ONT 
is “Discovered”)

Registration ID using a lineman’s handset (see below)

Set Registration ID Activation using Lineman’s Handset

To set the Registration ID using a DTMF Keypad on a standard 
lineman’s handset, complete the following steps:

g

     NOTE

The ONT does not need to be connected to the OLT during the 
Registration ID process.

Only POTS port 1 can be used for Registration ID configuration.

1. Perform an initial power-up on a new ONT.

g

     NOTE

At the start-up of the ONT, a 10-second Registration ID configu-
ration window is provided.

2. Wait for the indication that Registration ID configuration is 

available. The 

GPON

 LED will be flashing green on a 200 

millisecond interval when Registration ID configuration is 
available.

Label

Status

Indication

PWR

Off
Green

No power
No failure

GPON

2

Off
Green
Green Flashing

No power or not provisioned
Link stable
Linking in process

ETH 1-4

(YELLOW)

Yellow
Off

100 Mbps speed
10 Mbps speed

ETH 1-4

(GREEN)

2

Green
Green Flashing
Off

Valid link detected
Link activity detected
No link established

POTS 1-4

2

Off
Green
Green Flashing

Administratively shut down
Off-hook
Ringing

Содержание 1287802F1

Страница 1: ...SS 1 LASER PRODUCT INSTALLATION This section explains how to install the NID ground the NID route and attach the incoming Fiber and install the ONT in the NID There is also a section on connecting POTS and Ethernet services After unpacking the ONT inspect it for damage If damage is noted file a claim with the carrier and then contact ADTRAN For more information refer to the warranty f WARNING Read...

Страница 2: ...data the connection to the ONT is through the RJ 45 Ethernet connector For POTS the connection is made through 2 4 Two screw Terminal Bridges 2 for the 452 and 4 for the 454 or RJ 11 connections Installation Steps To install the ONT complete the following steps Mount the NID Enclosure Ground the NID Install the ONT Route the Fiber Connection Connect Power Alarm Install a Local Power Source Install...

Страница 3: ...Splice SC APC Bulkhead NID P N 1187770G1 g NOTE Clean all optical surfaces before connecting cables OptiTap NID P N 1187771G1 To install the fiber connection using the Optical Connector refer to Figure 5 and complete the following steps Figure 5 Optical Connector 1 Route the incoming fiber cable through the port identified in Figure 1 2 Connect the optical connector 3 Connect a fiber jumper from t...

Страница 4: ... 9 Power Alarm Connection and Routing 3 Terminate the 2 power leads Pins 6 and 7 and the five Uninterruptible Power Supply UPS leads see the pinout table 4 Connect the Power Alarm connector to the bottom of the ONT refer to Figure 8 5 Tie wrap and route these wires as shown in Figure 10 This will prevent the connector from coming loose when the ONT is closed Figure 10 Power Alarm Connector Install...

Страница 5: ...in any other fashion may cause harmful interference to radio communications ans is in violation of the FCC Rules part 15 CLEI TEL NUMBER PWR GPON POTS1 POTS2 POTS3 POTS4 Ethernet Connections POTS Connections Two Post Bridge Cable Routing Area POTS and Ethernet Port Captive Screw 2 Trim each wire to length 3 Connect the tip and ring wires to the terminal bridges 4 Insert the RJ 11 connectors from t...

Страница 6: ...r dial tone and flashes the GPON LED green for approximately 10 seconds with a cadence of 300 milliseconds on off before it continues its startup ranging process g NOTE If a failure occurs the ONT plays reorder tone and displays Invalid on the caller id display If the pattern is entered incorrectly the caller id displays Re enter if the first ID does not match the second Entering an invalid Regist...