6 Commissioning
6.1 Requirements
6.2 Switching the device on
By default, the device can be started using the
capacitive button
on the front side of the device. To do
so, the button must be pressed and held for
at least 1 s
, depending on the configuration in the
Configuration Center
:
The button has a blue-grey LED and indicates the following states:
−
LED lights up grey: Device is being supplied with power but is switched off.
−
LED lights up blue: Device is on.
−
LED flashes blue-grey: Device is in an energy-saving state.
This button can be activated and deactivated in the
Configuration Center
.
Alternatively, the device starts when the power supply is switched on. For this to happen, the "Autostart"
function must have been enabled in the
Configuration Center
(see the following section).
ATTENTION
Hazard due to condensation
Damage to electronic components caused by condensation resulting from temperature fluctuations.
•
Switch on the device only after it has acclimated to the ambient temperature.
WARNING
Hazard due to electric shock with fatal consequences
Before commissioning a device with an
AC voltage supply
, a
protective earth
conductor test
must be carried out
according to VDE 0701/0702
to ensure that
the protective earth is functioning optimally.