10.0 STARTING

10.1 INSPECTIONS
Before starting operation, make sure that the rules 
and regulations on the installation of these devices, 
especially with respect to the correct sizing of the 
water supply pipes have been complied with.
Before proceeding with the commissioning of the 
device must ensure that:
- security conditions and all the instructions contained 
in this manual have been complied with;
- securing the support bracket to the wall is stable and 
clear zones are free from any obstacle or materials, 
which hinder the easy accessibility of the apparatus;
- plumbing and electrical connections, with particular 
attention to the ground, they have been properly 
executed;
- the devices for loading, unloading and vent the 
system are in the correct operating conditions and 
have been adequately controlled;
- was made a thorough bleed air from inside of water 
pipes and the heat exchanger unit

10.2 CHECKS
Dare tensione tramite l’interruttore omnipolare di 
cui al precedente punto 3.3. Se l’apparecchio è 
comandato da un termostato ambiente, posizionare 
il dispositivo di regolazione dello stesso sul valore di 
temperatura che si desidera raggiungere in ambiente 
e, se il termostato è completo di commutatore delle 
tre velocità di ventilazione, controllarne il corretto 
funzionamento.

10.3 INFORMAZIONI ALL’UTENTE
Powering through the pole switch referred to in 
paragraph 3.3. If the unit is controlled by a room 
thermostat, set the adjustment device of the same 
on the temperature value you want to achieve in the 
environment and, if the thermostat is complete switch 
of the three-speed fan, check its correct functioning.

11.0 FAULTS OF OPERATION 

11.1 PRELIMINARY CHECKS
Before performing specific tests, make sure:

A)  power supply is properly connected and any
 

external regulation bodies such as the room

 

thermostat or timer, are operating properly;

B)  the shut-off valves, mounted on the water pipes,
 

are in the open position.

11.2 POSSIBLE DEFECTS

Here are the possible faults with the list of possible 
causes. In italics are briefly indicated repair or restore 
operations, which are the responsibility of skilled 
technical personnel.

11.3 FANS DO NOT WORK
A)
  The control systems and external control of the
 

equipment are dead (thermostats, on / off and the

 like);
-   Verify correct operation.
B)  The connection of power cables fan is damaged
 

or broken;

-  Restore the wiring correctly. Verify that the
  motor  is not burned and  in case replace it.

11.4 LOSS OF WATER FROM THE BATTERY
A)
  Water connections are not made correctly;
-  Restore the hydraulic connections ensuring
  the tightness of suitable materials.
B)  The exchanger has corrosion and / or lost estate;
-   Replace the heat exchanger with a new one,
  still looking for any external cause of the
 

problem (presence of corrosive atmosphere or

  aggressive substances in the environment)

11.5 FAN STOPS EVEN IN THE SITUATION
  OF OPERATING REQUESTA)
The motor thermal protection activated
-  Verify, through the use of an ammeter, that
  the absorptions of the motor does not move
  too much from the rated values, identify the
 

cause of overheating and possibly replace the

 fan.

11.6  NOISE OR VIBRATIONS DURING
 

  OPERATION

A) The fan is noisy and / or vibrating
- Check the correct rotation of the fan blades
 

and the presence of possible frictions. Remove

 

any dust deposits. Check the tightening of the

  screws that secure the motor to the grid and
  the grid itself appliance.

12.0 REPLACEMENT PARTS  
For the replacement of components is required 
specific technical skills, so it is recommended 
to alert the user to always contact an authorized 
Technical Service Centre.
For safety and quality reasons, it is recommended 
to be used for replacement original spare parts.

Содержание LC 16

Страница 1: ...1 Heaters blowers LC 16 20 28 40 56 TECHNICAL INFORMATION Heaters blowers LC...

Страница 2: ...2...

Страница 3: ...tips that you should carefully evaluate 3 The A2B Accorroni E G LTD accepts no responsibility for any damage caused by improper use to a use other than that prescribed and by an incomplete or approxim...

Страница 4: ...0 RULES FOR INSTALLATION 8 5 1 Positioning 8 5 2 horizontal flow heaters 8 5 3 heaters vertical flow 9 6 0 WATER CONNECTION 10 7 0 ELECTRICAL CONNECTIONS 10 8 0 TTECHNICAL DATA TABLES 11 9 0 WIRING 1...

Страница 5: ...adjustable manually The cover piece is made of painted sheet steel polyester powder in the long life guarantee In the rear are located according to the model one or two convection fans axial type with...

Страница 6: ...clean the outer parts of the appliance without first removing the power supply at the main switch do not leave the appliance exposed to the elements do not place objects on the unit do not touch the m...

Страница 7: ...ng of opposite flow directions c that the installation location allows accessibility to the appliance parts subject in maintenance The optimal installation height is between 2 4 and 3 5 m and is under...

Страница 8: ...for the main device Possible Shutdown It is banned the use of gas and or water pipes for the fixing of the unit on the ground A2B Accorroni is not responsible of any damage caused by lack of groundin...

Страница 9: ...ds on its activation and a fig 6 The heaters of the LC series can be provided with support brackets which facilitate the positioning in place Fig 7 The LC unit heaters are suspended vertically project...

Страница 10: ...city with a contact gap of at least 3 mm for any general standstill The use of gas and or water pipes for the appliance to be earthed is not allowed The manufacturer is not liable for any damage cause...

Страница 11: ...0 C 39 65 44 98 50 32 55 84 80 C 49 64 54 98 60 47 66 17 Yield heating T 20 C Description Air Temp entry C 20 15 10 5 Air flow m h 60 C 26 64 31 87 36 92 42 39 65 C 31 72 36 87 42 21 47 65 70 C 36 90...

Страница 12: ...ry Heating flow kW air temp variable d b C 2250 Water in entry Heating flow kW air temp variable d b C Table 1 Heating LC 40 Yield heating T 5 C 20 15 10 5 45 C 20 81 25 78 30 94 36 28 50 C 25 66 30 7...

Страница 13: ...flow m h 60 C 39 30 46 13 52 96 60 31 65 C 45 93 52 76 59 83 67 15 70 C 52 55 59 63 66 70 74 01 80 C 65 80 72 88 80 15 87 71 Yield heating T 20 C Description Air Temp entry C 20 15 10 5 Air flow m h...

Страница 14: ...16 20 28 WITH CONSENT THERMOSTAT Connections to be made Connections to be made LEGEND M Clamp C Condensator b Blue m Brown n Black gv Yellow green Mv Motor fan LEGEND M Clamp Tr Consent thermostat C C...

Страница 15: ...20 28 WITH AMBIANCE THERMOSTAT SUMMER MODE VENTILATION ONLY Connections to be made Connections to be made LEGEND M Clamp Tr Consent thermostat C Condensator b Blue m Brown n Black gv Yellow green Mv M...

Страница 16: ...MV2 MV1 MV2 LEGEND M Clamp C Condensator b Blue m Brown n Black gv Yellow green Mv1 Motor fan 1 Mv2 Motor fan 2 LEGEND M Clamp Tr Consent thermostat C Condensator b Blue m Brown n Black gv Yellow gre...

Страница 17: ...AMBIANCE THERMOSTAT winter mode MV1 MV2 MV1 MV2 To take off the bridge between 0 and 4 To take off the bridge between 0 and 4 LEGEND M Clamp Tr Consent thermostat C Condensator b Blue m Brown n Black...

Страница 18: ...erly connected and any external regulation bodies such as the room thermostat or timer are operating properly B the shut off valves mounted on the water pipes are in the open position 11 2 POSSIBLE DE...

Страница 19: ...071 723991 13 0 MAINTENANCE 13 1 MOTORS The engines are fitted with permanently lubricated bearings Therefore they do not need special maintenance 13 2 BATTERIES Once a year before the season of use...

Страница 20: ...of radio disturbance characteristics of electrical equipment and similar power or thermal tools and electrical appliances EN 55014 1 2006 Complies with the measurement methods for electromagnetic fie...

Страница 21: ...21...

Страница 22: ...22 A2B Accorroni E G s r l Via d Ancona 37 60027 Osimo An Tel 071 723991 r a Fax 071 7133153 web site www accorroni it e mail a2b accorroni it...

Отзывы: