31
5
4
3
1
2
1
3
2
4
Figure 101. Medium voltage cable cover
1. Cable cover
2. Cable seal
3. Cable support
4. Hexagonal nuts with flange 9ADA289 M6 - steel 8 A2F
5. Cheese-head Torx plus screw. Screw M6x12 Fastite200005HQ -BA
Operations
1
. Dismantle the cable clamps, cable guide splines, fairleads
and the floor sheet
a) Unscrew the eight bolts on the floor and remove the bottom
plates.
Figure 102. Dismantling completed
5. Cable connections
5.1 Installing the cables
NOTE
The clamping screws are optional.
NOTE
The position of the medium voltage cables
are positioned L1, L2 and L3 front to back.
5.1.1 Installing the cables
Parts
Figure 100. Parts
1. Floor sheet
2. Fairleads
3. Cable guide spline
4. Cable clamping screw