Transport
The UPS is packaged on a pallet suitable for handling with a forklift.
The UPS must be moved in
upright position
.
Do not tilt cabinets
more than +/- 10°
during handling.
Move the UPS in its original package to the final destination site
.
Do not stack other packages on top
: This could damage the UPS.
Forklift
Fig. 4.1-1 Position of the forklift when moving the unpacked UPS
Forklift
The UPS must be lifted with a forklift in upright
position.
Take note of the
Center of Gravity
marked on the
package.
Warning!
Check for sufficient floor and elevator loading
capacity.
Transport UPS only in upright position.
Do not stack other package on top of the UPS.
Crane
Fig. 4.1-2 Position of the carrying belts when moving the unpacked UPS
Crane
If the UPS has to be lifted by crane, use suitable
carrying belts taking note of the
Center of Gravity
marked on the package.
Take all necessary precautions to avoid damage
to the cabinet while hoisting the UPS
.
Warning!
When loading / unloading and when moving
the UPS, it is forbidden: