5. If you use an Ethernet cable, make sure that the internet connection is available
for an approved service engineer and the network operating center of the
manufacturer.
6. Make sure that the cable slack is sufficient to guide the cables in the cabinet.
.
7. Prepare the foundation for the cabinet. Refer to section
.
5.2.2
Control the space and airflow around the cabinet
1. Make sure that the floor space agrees with the requirements. Refer to section
.
2. Make sure that the air flow inlet and outlet cannot get blocked. Think of snow or
objects.
5.3
Prepare the foundation
5.3.1
Prepare the foundation - general procedure
1. Select the correct foundation, based on the surface you install the cabinet on.
2. Embed the cables in the ground with or without a cable duct. Refer to the local
rules.
5.3.2
Prepare a standard prefab foundation
Preliminary requirements
•
Prefab foundation. Refer to section
.
Procedure
1. Make the foundation (A). Do one of
these steps:
•
Contact the manufacturer to order
the foundation for your EVSE.
Refer to section
.
•
Make the foundation according to
the specifications.
2. Dig the hole for the foundation (B). For
the specifications, refer to section
.
Caution: Make sure that the
top surface of the
foundation is above the
ground level, to prevent
intrusion of water.
3. Guide the cables to the locations (C).
4. Install the foundation in the hole.
5. Put the cables through the openings (D) in the foundation. Apply the full cable
slack.
6. Fill the foundation with gravel or another substance to prevent rodents to enter
the cabinet.
B
C
A
D
Installation
26
BCM.S1102.0-EN | 001