RTU500 series Remote Terminal Unit
Test & Simulation
Inputs and Outputs view - elements of the user interface
ABB AG - 1KGT 150 924
V000 1 | 4-7
Figure 46: Single forcing example
It is also possible to simulate a sequence of signals. The checkboxes in the last column are used
with this purpose. If the user selects multiple checkboxes in different rows (even in different pages
of the grid) and then clicks on any "Simulate", "Se" or "Ex" button, all the selected signals will be
simulated sequentially, from top to bottom (Fig. 47). The "All" button at the top of the column selects
(or deselects) all checkboxes in the current page of the grid.
Figure 47: Multiple forcing example
A dialog will be prompted before starting a multiple forcing (Fig. 48). This may avoid undesired
sequence simulation.
Figure 48: Multiple forcing dialog
4.4.2
Multiple simulation interval
It is possible to specify the time interval between each signal in a multiple simulation sequence. This
time span is defined by the user in seconds. An interval less than a second is also possible to be
defined (for instance "0.1" seconds).
4.4.3
STOP button
The user has the possibility to stop a running simulation sequence by clicking on the STOP button.
This action will also disable the Test Mode and set the RTU500 back in normal operation.
Содержание RTU500 series
Страница 1: ...RTU500 series RTU500 series Remote Terminal Unit User manual Web server Release 12 ...
Страница 36: ...Diagnostics RTU500 series Remote Terminal Unit Hardware Tree 3 6 1KGT 150 924 V000 1 ABB AG ...
Страница 88: ...USB RNDIS Driver Installation RTU500 series Remote Terminal Unit Windows 7 9 8 1KGT 150 924 V000 1 ABB AG ...