Option description and instructions
3ADW0005Q964 E-Stop cat.1 without opening mains contactor en b
+Q964 Start-up and acceptance test
You need the Drive composer PC tool or a control panel to perform the start-up and acceptance test.
Initial status: Make sure that the drive is ready for use, that is, you have done the tasks of the drive
start-up procedure. See the hardware manual.
Action
, page
. If you ignore them, injury or
death, or damage to the equipment can occur.
Checks and settings with no voltage connected
If any connections of the emergency stop circuit have been changed on site (such as
wiring of additional emergency stop buttons, connection of shipping splits of large
drives, etc.), verify that the connections are correct with the appropriate circuit
diagrams.
Check that the hardware settings relevant to the safety function are set as defined in
section
on page
OK
Settings with voltage connected
Check that the parameters relevant to the safety function are set as defined in section
Ensure that the motor can run and be stopped freely during the test.
Start the drive and ensure that the motor is running. If possible, use a motor speed close
to the maximum speed of the application.
Push the emergency stop button [S61] (if installed).
Ensure that the drive stops the motor by decelerating and displays a warning. For a
description of the messages, see the firmware manual of the drive.
Ensure that the indication lamp [P62] switches on (if installed).
Ensure that you cannot restart the drive and motor from any control location: Ensure
that the motor does not start even if you switch the start signal off and on or push the
start key of the panel.
Turn the emergency stop button [S61] until it releases and returns to the up position
Push the emergency stop reset button [S62]. Ensure that the emergency stop reset
indication lamp [P62] switches off (if installed).
Switch off the drive start signal. If a fault message is generated, reset the drive. See
section
Restart the drive and motor and check that they operate normally.
Repeat the test from each operating location (each emergency stop button and reset
button).
Fill in and sign the acceptance test report which verifies that the safety function is safe