2TSA451011P0000 Rev-B
© 2020 Emax 2 Retrofill Circuit Breakers 600A-4000A |
29
Install Cassette (Landed Wires)
Danger
It must be ensured that the supply power to
the
compartment
is
turned
off/
compartment is de-energized for all the
incoming and outgoing circuits of the LVS
prior to any work being conducted on it.
During the installation and related work on
the equipment, it must be ensured that the
operator is using the prescribed PPE for the
specified tasks.
Ensure only qualified personnel install, operate, service and maintain all electrical
equipment.
Fig 53 shows the front view of the AKD-5 cassette, ready for installation
Figure 52 & 53
AKD-5, AK50
Fig 52. Cassette Projected from Switchgear Fig 53. Cassette racking on Switchgear rails
Figure 54
Switchgear and Cassette assembly (Front View)