Operation Manual / A150-M56/66/57/67 - A155-M..
4 Commissioning / 4.3 Commissioning after taking out of operation
© Copyright 2021 ABB. All rights reserved.
HZTL4032_EN
Rev.Q
January 2021
4.3
Commissioning after taking out of operation
If present
u
Remove cover plates (blind flanges) from the compressor casing, the gas inlet and the
gas outlet.
Version with compressor wheel cooling:
u
Remove the locking screw on the cooling air connection and fit the cooling air line.
General
u
Check the exhaust gas pipe before and after the turbine for combustion residues or wa-
ter residues and clean it. Remove any foreign objects that may be present.
u
Check and clean filter silencer or air supply line, and remove any foreign objects that may
be present.
u
Put engine-side oil circulation to the turbocharger into operation.
u
Prepare the turbocharger for operation (see
u
The turbocharger is now ready for operation.
Page
43
/
194
Содержание HT604364
Страница 2: ......