Start-up
Contents of this chapter
The underlined tasks are needed for certain cases only. The default device designations (if
any) are given in square brackets, for example, DC switch/disconnector [Q11]. The same
device designations are also used in the delivery-specific circuit diagrams.
Note:
Always refer to the delivery-specific circuit diagrams when proceeding with the start-up.
WARNING!
Only qualified by ABB electricians/engineers are allowed to do the work described
in this chapter. In addition, the electrician/engineer must know the energy storage
system he is about to take into use, and the DC/DC converter control program and
operation principle. Obey all the safety instructions in
Safety instructions for ACS880
multidrive cabinets and modules
(3AUA0000102301 [English]) and
. If you ignore the safety instructions, injury or death, or
damage to the equipment can occur.
Before you start, connect a control panel to the DC/DC converter unit. We recommend that
you also have a PC with a drive commissioning tool (Drive composer) connected.
8
Start-up 63
12
Содержание ACS880-1607LC
Страница 1: ... ABB INDUSTRIAL DRIVES ACS880 1607LC DC DC converter units Hardware manual ...
Страница 2: ......
Страница 4: ......
Страница 12: ...12 ...
Страница 32: ...32 ...
Страница 38: ...38 ...
Страница 60: ...60 ...
Страница 80: ...80 ...
Страница 90: ...90 ...
Страница 102: ...Unit with 1 R8i converter module 102 Dimension drawings ...
Страница 103: ...Dimension drawings 103 ...
Страница 104: ...Location and size of energy storage connection terminals 104 Dimension drawings ...