86 Installation checklist
WARNING!
Obey the instructions in chapter
. If you ignore
them, injury or death, or damage to the equipment can occur.
NOTICE!
The field engineer should confirm that the power cables are connected
to the correct bus bars before switching on the main power. Once the main power
direct reach the output bus bars by wrong connections, the power modules would
be irreversible damaged.
Checklist
Do the steps in section
Precautions before electrical work
on page
before you start the
work. Go through the checklist together with another person.
Mechanical installation
1.
The infrastructure of the electric room is finished and the installation site is sufficiently ventilated
or cooled and dehumidification to ensure the converter can running at the appropriate
temperature and humidity.
2. The wall behind the unit is of non-flammable material. Please take the photo and send back.
3. There is enough free space above the drive to enable cooling air flow, service and maintenance.
See layout drawing. Please take the photo and send back.
4. Ambient operating conditions meet the specifications given in chapter
5. Drive installed according to the instructions in this manual (Chapters
and
)
6. Drive securely fastened to the floor
7. INU cabinet and transformer cabinet have finished combination.
8. The floor that the unit is installed on is of non-flammable material, as smooth as possible, and
strong enough to support the weight of the unit. Check the floor flatness with a spirit level. The
maximum allowed deviation from the surface level is 5 mm in every 3 meters. Level the
installation site, if necessary, as the cabinet is not equipped with adjustable feet.
9. Fan units installed
Содержание ACS580MV
Страница 1: ...ABB industrial drives Hardware manual ACS580MV drives 200 kW to 6300 kW 6 kV to 11 kV...
Страница 4: ......
Страница 10: ...10...
Страница 50: ...50 Control system and interfaces...
Страница 52: ...52 Guidelines for planning the electrical installation...
Страница 77: ...Electrical installation 77 Power cable entry from top 1 screen extensions to ground 1...
Страница 90: ...90 Installation checklist...
Страница 125: ...Maintenance 125 5 Disconnect the fiber optic links from the power module 1 Hoist 2 screw M8X20 1 2...
Страница 127: ...Maintenance 127 stops it again 10 Connect the second lifting belts to the lifting eyes provided on the power module...
Страница 142: ...142 Maintenance...
Страница 144: ......
Страница 146: ...Contact us 2UBB004520 Rev E EN 2019 06 27 www abb com drives www abb com drivespartners...