background image

                                      

 

20/21C Series  

Ball Valve 

Installation & Maintenance Manual

 

 

 

 

03/30/21 

www.atcontrols.com 

IOM7013 REVISION 01

 

  

SCOPE 

 
CAUTION 
 

 

For your safety, read this manual before installation or service. All persons involved in the installation/removal and 
disassembly/reassembly of the valve should wear the proper personal protective equipment.

 

 

Before installing or servicing, please ensure the line pressure has been relieved and any hazardous fluids have been drained 
or purged from the system.

 

 

Ensure that all Lockout and Tagout procedures for the system have been properly implemented.

 

USE 
 

 

Maximum results and long life of valves can be maintained under normal working conditions and according with pressure/ 
temperature ratings and corrosion data chart.

 

INSTALLATION 

 
GENERAL INFORMATION FOR INSTALLATION 

 

 

The valve can be installed in any position on the pipeline.  

 

Before installation of the valve, the pipe must be flushed clean of dirt, burrs, and welding residue or the seats and ball 
surface will be damaged. The pipe must be free from tension and in proper alignment. Check to ensure that all connections 
are free from defects.  

 

Use conventional sealant, such as hemp core, Teflon, etc. on the threads.  Apply wrench only on the hexagon of the valve 
ends.  Tightening by using the valve body or lever can seriously damage the valve.  In some applications, screwed valves are 
back welded on site.  These valves must be treated as per instructions for weld end valves before back welding.  

VALVE OPERATION 

 

 

To OPEN the valve: turn the handle counterclockwise until the handle is parallel with the pipeline and the

 

handle has 

contacted the handle stop.  

 

To CLOSE the valve: turn the handle clockwise until the handle is perpendicular with the pipeline and the handle has 
contacted the handle stop. 

 

A handle lock is incorporated into the handle 

DISASSEMBLY OF VALVE 

 

 

Remove valve from pipeline. 

 

Place valve in its fully open position. Remove end cap (Item #2) of valve. 

 

Close valve. Remove seats (Item #8), Joint Gasket (Item #13), and Ball (Item #3).

 

 

Remove Stem Nut (Item #5), Lock Washer (Item #6), Handle (Item #7), Gland Nut (Item #9). Remove Stem (Item #4) by 
holding the bottom of the stem and pushing the stem through the Body (Item #1).

 

 

Remove Thrust Washer (Item #11).

 

 

Examine all parts for damage. If there is damage to any parts, these parts shall be replaced when reassembling valve to 
ensure proper operation of valve.

 

    RE-ASSEMBLY OF VALVE 

 

 

Place new thrust washer (Item #11) onto Stem (Item #4) and place Stem into valve.

 

 

Re-install Gland Nut (Item #9) and tighten to the torques listed in Table A.

 

Отзывы: