R-30 R
2.3. Initial Start-up - The Control Valve
1.
Make sure that the upstream and the downstream isolation valves are closed [
2
] and [
2
A].
2.
Turn off the manual
2
-way ball valve at the downstream [
3
B] port of the valve.
3.
Slowly open the upstream isolation valve [
2
].
4.
Turn on the manual
2
-way ball valves of the upstream [
3
A] and the downstream [
3
B] ports of the valve.
5.
Slowly open the downstream isolation valve [
2
A], water starts to flow to the pipeline.
6.
Turn the adjusting screw [
4
A] clockwise until the downstream pressure reaches the required level.
Important note:
In case of high upstream pressure,
carefully monitor the downstream
pressure while opening the
downstream isolation valve; make sure
not to expose the pipeline to excessive
pressure.