IN0020
Revision 05
004799
– 1 of 8
POWER PERFORMANCE PASSION
Installation Notes
SP PRO Grid Fail - Generator Backup Kit
Installation Note
Introduction
This installation note details the addition of the Grid fail-Generator backup kit to the SP PRO
inverter. The kit is only suitable for the small range (SPMC) of SP PRO AU or GO series (Series
II) in a single phase or a three phase Advanced Multiphase Solar Hybrid installation.
NOTE
:
Three kits are required for a three phase Advanced Multiphase Solar Hybrid installation.
The Grid fail - Generator Backup ONLY operates with Auto Start generators and CANNNOT BE
USED with manual start generators. A three phase generator must be used in a three phase
installation.
When the Grid fail-Generator backup kit is installed into the SP PRO, the system allows for the
connection of an auto start backup generator that is automatically started and stopped by the
SP PRO as required during a grid outage.
SP PRO Models
Grid fail – Generator backup
kit, single phase.
Grid fail – Generator backup
kits, three phase.
SPMC 240-AU, 004723
1 off SPMCA-GFGB-2448, 005268 3 off SPMCA-GFGB-2448, 005268
SPMC 241-AU, 004724
SPMC 481-AU, 004725
SPMC 482-AU, 004726
SPMC 1201-AU, 004722 No Kit Available
No Kit Available
Preparation
When installing a single phase system, make sure one Grid Fail Generator Backup kit (005268) is
on site.
When installing a three phase Advanced Multiphase system, make sure three Grid Fail Generator
Backup kits (3 x 005268) are on site.
-
If installing a three phase system, make sure the AMP Three Phase kit is on site
(Order code 005304)
This document needs to be read in conjunction with the SP PRO Instruction Manual and SP LINK
instruction manual (both found in SP LINK Help menu)
Additional information
Selectronic web site –
http://www.selectronic.com.au
or contact the Selectronic Sales Team
This document applies for SP PRO Series II Rev 21 and above