background image

 

 

 

VOZROZHDENIE LLC 

 

 

  OKPD2 27.90.40.190 
 

  

TU 27.90.40-001-33120038-2018

 

 

  APPROVED 
 

  

VZR.248100.000 AS

 

 

 

 

 

 

SWING GATE 

MODEL K-14 

 

 

VZR.248100.000 IG 

INSTALLATION GUIDELINES 

20 pages 

 

 
 
 
 
 
 
 
 
 

2019

Summary of Contents for K-14

Page 1: ...VOZROZHDENIE LLC OKPD2 27 90 40 190 TU 27 90 40 001 33120038 2018 APPROVED VZR 248100 000 AS SWING GATE MODEL K 14 VZR 248100 000 IG INSTALLATION GUIDELINES 20 pages 2019 ...

Page 2: ...nspection 6 3 4 Requirements to the product installation place 7 4 INSTALLATION AND DE INSTALLATION OF THE PRODUCT 8 4 1 Required equipment 8 4 2 Product installation 8 4 3 The product dismantling 10 5 CONNECTION AND ADJUSTMENT OF THE PRODUCT 11 5 1 Connection of power supply 13 5 2 Connecting control panel 14 5 3 Connection of access control system optional 14 6 comprehensive examination 17 6 1 V...

Page 3: ...g the product it is necessary to additionally read Operation Manual VZR 248100 000 OP In connection with permanent work on improvement of the product changes can be made to the product design which are not included in this edition of Installation Guidelines Following abbreviations are used in this document OM Operation manual IG Installation guidelines PSU power supply unit CP control panel ACS ac...

Page 4: ...starting installation work completely disconnect power supply of the product IT IS PROHIBITED TO INSTALL POWER SUPPLY UNIT INSIDE THE PRODUCT AS IT MAY CAUSE ELECTRIC SHOCK TO PEOPLE INSTALL THE PRODUCT OUTSIDE DRY AND HEATED ROOMS PREVENT OR ACCELERATE THE MOVEMENT OF THE PRODUCT LEAF DURING SWITCHING ON OFF ANTI PANIC MODE AP APPLY FOR THE PRODUCT CLEANING PASTES AND LIQUIDS CHEMICALLY AGGRESSIV...

Page 5: ...ices instructed on safety at work with electrical installations for voltage up to 1000 V ATTENTION FAILURE TO COMPLY WITH THE SAFETY REQUIREMENTS SPECIFIED IN THIS SECTION MAY RESULT IN DEATH AND DAMAGE TO HEALTH COMPLETE OR PARTIAL LOSS OF PERFORMANCE OF THE PRODUCT AND OR AUXILIARY EQUIPMENT ATTENTION MANUFACTURER DISCLAIMS ANY LIABILITY FOR DEATH AND DAMAGE TO HEALTH COMPLETE OR PARTIAL LOSS OF...

Page 6: ...ation at negative temperature the product should be held in a room with normal climatic conditions for 12 hours Loading and unloading operations should be carried out in compliance with safety regulations 3 2 Rules of the unpacking of the product 3 2 1 Perform visual inspection of the packaging The packaging should not have visible damages 3 2 2 Open transportation box unpack and inspect completen...

Page 7: ... to make Act of claim 3 3 4 Figure 1 overall dimensions of the product Figure 1 overall dimensions of the product 3 4 Requirements to the product installation place ATTENTION TO AVOID WAVING AND OR OVERTURNING DURING OPERATION INSTALL THE PRODUCT SECURELY IN CASE OF PRODUCT INSTALLATION ON FLOOR OF LOW STRENGTH TAKE MEASURES FOR FLOORS STRENGTHENING IN THE PLACE OF INSTALLATION ...

Page 8: ...h S6 4 cross screwdriver 5 plumb or level 6 steel shims for products leveling 4 2 Product installation ATTENTION CAREFULLY READ THIS SECTION OF THE MANUAL BEFORE MOUNTING THE PRODUCT ATTENTION IT IS RECOMMENDED TO MARK MOUNTING HOLES BY MATCHING TO HOLES OF FLANGE OF POST BASE OF THE GATE WITH ALREADY INSTALLED LEAF 4 2 1 Prepare horizontal platform at the product installation site 4 2 2 Prepare c...

Page 9: ...Depth of the holes for embedded parts should exceed anchor length by 5 mm Insert the anchors into the holes 4 2 5 In cable duct or channel lay control panel connection cable power supply cable and if provided cables for ACS and security and fire alarm system 4 2 6 Install the gate post on the prepared place 4 2 7 Insert in the gate cables from control panel power supply and if necessary cables for...

Page 10: ...th 4 M10 screws by screwing them into the appropriate anchors with a wrench S6 4 3 The product dismantling 4 3 1 The product dismantling for sending for inspection or repair should be performed in the following order 1 turn off the product power 2 disconnect the product from the power supply 3 disconnect the cable part of the product from the additional cables 4 dismantle the product from the inst...

Page 11: ... Figure 3 components arrangement on the gate post Connection of power supply control panel and ACS should be carried out by means of the cross board Figure 3 Components arrangement on the gate post 1 Cover 2 Insert 3 Indication panel 4 Body housing 5 Cap 6 Glass 7 Upper housing 8 Location of cross board ...

Page 12: ...de p 5 3 J1 installed Potential control mode p 5 3 J2 installed Direction of the leaf opening in anti panic mode left right J2 is not installed Direction of the leaf opening in anti panic mode changes to the opposite relative to the mode with the installed jumper anti panic mode is automatically switched off after 20 minutes of switching on J3 jumper is used to enable regular speed of leaf opening...

Page 13: ...TTENTION IT IS NOT RECOMMENDED TO INSTALL POWER SUPPLY UNIT AT A DISTANCE OF MORE THAN 25 M FROM THE PRODUCT The product is powered by voltage of 24V DC It should be taken into account that the voltage drop increases with the length of the supplied cable operating voltage range is given in Operation Manual VZR 248100 000 OP Install the power supply unit in a place where there is free space for ope...

Page 14: ...ording to terminal markings given in Table 2 Table 2 Marking of terminal for control panel connection Terminal marking Wire color 24V Red CL Yellow CH Green GND Blue 5 3 Connection of access control system optional ACS controller should be connected to a group of terminals Access Control System on the cross board ATTENTION THE PRODUCT IS NOT INTENDED FOR PERSONNEL TIME TRACKING Marking of terminal...

Page 15: ...ide single one way passing If both inputs are closed the leaf is open in the direction defining by input which was closed first In case when passing did not occur the product will automatically enter Stop mode after 10 seconds in pulse control mode In potential control mode the gate will be open as long as there is a signal at its input from the controller to allow passing ATTENTION IN CASE OF STO...

Page 16: ...nnection NC and COMM normally closed connection Triggering of one of the terminal groups indicates opening of gate in corresponding direction and its return in initial closed state PassOk1 right PassOk2 left D1 and D2 LEDs indicate relay status PassOk1 right and PassOk2 left The cross board has relay output for ACS which work as dry contact Status NO and COMM is normally open connection its contac...

Page 17: ...uct readiness for use 6 1 1 Check fastenings of parts and units of the product 6 1 2 Check fastenings of all cables 6 1 3 Turn on power supply of the product and carry out check of operation by making several test cycles 6 1 4 If any extraneous noise and violations of operation modes are not found the product is ready for operation ...

Page 18: ...ve of organization which performed installation work demonstrates reliability of the product installation 2 mark on the product installation are made in VZR 248100 000 DTS Product status record in the section Product movement in the course of operation 3 Data on installation section of 248100 000 DTS Product status record on the product is filled in 4 Act of acceptance in operation is made out ...

Page 19: ...VZR 248100 000 IG K 14 Swing gate Installation Guidelines 19 ...