Introduction

To align the holes in the 8/10/12RESV(L) enclosures

with the threaded inserts in the mounting pad, the

enclosure holes may need to be increased in size.

Before enlarging the holes, obtain four washers

required for the enlarged hole size.

Follow the instructions and safety precautions in this

service bulletin to ensure that the hole alignment is

accurate. Refer to the mounting pad installation

instructions, TT-1619, as needed for additional

information.

Special Tools Needed

D

Drill

D

19/32 in. drill bit

D

Metal File

D

Washers, Qty. 4: 10.5 mm ID x 20.0 mm OD x

2 mm thick, zinc plated

Kohler Part Number:

M125A-10-80

D

GM84772

touch-up paint bottle or

GM84771

touch-up paint spray can

10.5 mm

20.0 mm

2.0 mm

Figure 1-1

M125A-10-80 Washer Dimensions

Safety Precautions

Unbalanced and elevated weight.

Improper lifting can cause severe

injury or death and equipment

damage.

Do not lift the generator set from the

engine or alternator eyes. Never

stand under a unit being lifted.

Always maintain a safe distance from

the unit being lifted.

See the lifting instructions in the

installation manual that was provided

with the unit.

WARNING

Installation Procedure

1.1 Use a 19/32 in. drill bit to enlarge the existing holes

in the enclosure base.

Note:

If the holes are not large enough, use the drill bit

to carefully enlarge the holes further. Use

extreme care to avoid damaging the enclosure

base.

1.2 File any burrs and cover exposed metal with

touch-up paint.

1.3 Align the enclosure with the mounting pad inserts.

1.4 Use the four bolts that come with the concrete pad

and

M125A-10-80

washers to secure the

generator to the mounting pad.

Note:

Place the washer between the bolt head and the

enclosure base.

Routing

Initial

Here

Service

Manager

Sales

Manager

Parts

Manager

Technician

No. 1

Technician

No. 2

Technician

No. 3

Return

This to

Reviews: