background image

 

 

 

FLORLOK®

 Portable Dance Floor laying instructions 

 

The Florlok® portable dance floor consists of 

FULL

 and 

HALF

 panels which are set up in a “brickwork” fashion 

which in turn gives the floor its strength without the need for tools and/or screws. Panels have “lugs” attached 

on three sides (the side with three lugs are known as the “

END LUGS

”) which interlock with the adjacent 

panels and one side without lugs. Along the other two sides are five 

LUGS

 which interlock with panels used in 

the rows above and below. The top row consists of 

FULL

 panels and then every even row (row 2, 4, 6 etc.) 

starting and ending with 

HALF 

panels. The 

first 

panel of each row is laid with the 

“END LUGS” 

pointing left and 

all following panels with the 

“END LUGS” 

pointing right. Surrounding the panels are then aluminium edging 

strips also supplied in 

FULL

 and 

HALF

 lengths as well as the 

CORNER

 edges. 

It helps to plan the dance area before laying panels to ensure you have the floor centred with the room itself 

or other furniture such as a stage unit. 

 

Using the attached floor plan as a guide for your size of floor lay the floor as follows: 

 

1.

 

ROW 1: The first 

FULL

 panel is laid at the top left hand corner of the floor with the three “

END LUGS” 

pointing to the 

left

 and then the second 

FULL

 panel is laid alongside the first with the 

“END LUGS” 

pointing to the 

right

. The first two panels just sit next to each other. The third and the rest of the top 

row 

FULL

 panels can now be laid with the 

“END LUGS” 

pointing to the 

right

 with the bare side of the 

panel sitting on top of the previous panels 

“END LUGS”

.  

 

 

 

 

 

 

 

! Ensure that the panels are flush along the top row. 

2.

 

To help keep the top row in place, now fit the edging pieces across the top row starting from the left 

hand side with a 

HALF 

edge and then a 

FULL

 edge which will span the joint of the first two 

FULL

 

panels. Continue fitting the 

FULL 

edging pieces with a 

HALF 

edge being used at the end of the row to 

fit flush with the right hand side.  

 

 

 

 

 

 

 

 

 

 

! Fit the edging by pushing the lugs under the panel rim at an angle and lowering the edge into place. 

DO NOT FORCE but adjust. 

 

 

1st panel 

2nd panel 

3rd panel 

4th panel 