General: These instructions detail the proper procedure for
installing C&D Technologies' Powercom Division (C&D) NEBS
compliant battery racks. The following describes how to 
locate, assemble, and load open-frame racks for C&D 
battery mounting applications. Proper attention to these
instructions will help ensure safe, trouble-free performance.  

Rack Location: Locate racks in a clean, cool, dry place so 
the batteries are not affected by sources of radiant heat, 
such as sunlight, heating units, radiators, steam pipes, etc.
Variations of more than 5F (3C) between cells may 
cause the battery to float and operate at different voltage
ranges. Top rows of batteries in multiple-tier configurations
tend to operate at slightly higher temperature than those 
on lower tiers. Always provide adequate ceiling clearance 
for ventilation and maintenance. 

Anchoring: To provide stability, safety, and seismic integrity,
racks must be securely anchored to the floor. Anchor bolts 
are to be installed per vendor’s specifications and in 
accordance with applicable codes. Do not attach rack to 
walls without consulting C&D first. Mounting holes are 
provided in the base of each frame.  All frames must be
secured to floor using all anchor locations. It is the 
responsibility of the customer to secure racks in 
accordance with allowable floor loading, applicable 
codes and regulations. 

Grounding: Rack grounding provisions are integrated into 
the base of each frame. Two 7/16” (11mm) diameter thru holes
are located at the center of the frame's bottom cross member
and may be used to secure a standard NEMA lug. These 
two holes have 1.0” (2.54cm) between centers and have 
been masked and are free of powder coating to allow for 
electrical contact. Frame to frame grounding integrity is
accomplished via the lower support rail, attached to 
each frame with an Internal/External “star” washer. 

NOTE: 

Floor mounting hardware is to be determined in 
accordance with applicable building codes, not by 
C&D.  For proper certification, a floor anchor must 
be a minimum or equivalent to an Hilti HSLM12-25.

CAUTION:

Do not install batteries until the rack has been properly
installed, with all bolts tightened to specified torque and
frames anchored to the floor.

Do not use oil, grease or any other lubricating agent as a
lubricant for cell installation. This could void the warranty.
Lubrication is usually not required due to the low friction
interface of the insulated covers. If necessary, a small
amount of water or unscented talcum powder can be
applied to the rail covers to reduce friction.

FIGURE #1

End view of 2-tier and 2-tier/2-row racks.

D/11

“L” SERIES

NEBS COMPLIANT

STANDBY BATTERY RACKS 

ASSEMBLY INSTRUCTIONS

RSO1942  2/21/03  2:24 PM  Page 1

Summary of Contents for L Series

Page 1: ...responsibility of the customer to secure racks in accordance with allowable floor loading applicable codes and regulations Grounding Rack grounding provisions are integrated into the base of each fram...

Page 2: ...ufacturers instructions for tools required to install floor anchoring hardware INSTALLATION DETAILS Bolted connection details are located at the end of installation manual for reference Torque values...

Page 3: ...support rail s in location using supplied 3 8 bolt lock washer and serrated strut nut Ensure that the strut nut has properly engaged the strut 3 Installing Support Rails Install support rails from th...

Page 4: ...ings 7 Battery Restraint Bracket Assembly Install the tie rods and covers of the battery restraint bracket assembly See Detail 4 If batteries are completely installed before this step installing tie r...

Page 5: ...en side restraint rails and covers to batteries If there is interference between battery and rail confirm that the battery is pushed to the back for single row and towards the center for double row ra...

Page 6: ...ll and inter unit connectors and cable assemblies as specified by the battery arrangement Refer to battery installation manual for more detail on battery connections ADDITIONAL INSTRUCTION FOR MULTI R...

Page 7: ...0 Frame Typical for Both Side Restraint and Bottom Rails Serrated Nut Strut For Support Rails or Side Rails Lock Washer 3 8 Bolt 3 8 16 x 1 00 Bolt 3 8 16 x 1 00 Note Bolt head must be facing Battery...

Page 8: ...rrated Strut Nut 5 16 18 Nut and 5 16 Lock Washer 3 8 16 x 1 00 Bolt and 3 8 lock washer DETAIL 5 End Restraint Assembly Detail 2022 C D Technologies Inc Any data descriptions or specifications presen...

Reviews: