background image

PECO/ECO TOOL BOX TALK 

 

TOOL BOX TALK 

Before attempting to operate the Peco / Eco please carry out the following procedures.  

PRE-OPERATION CHECKS 
1.

  

Visually inspect the WR machine; check for signs of damage to structure including castors, wheels, 
operating handle. 

2.

  

Position the WR machine safely; ensure there are no overhead obstructions or dangers. 

3.

  

Ensure ground conditions are suitable. The WR machine should be used on hard, level surfaces up to 
3° that will support the WR machine and safe working load. 

4.

  

Ensure castors are locked before entering platform. 

5.

  

Check operating handle is working correctly by stepping into basket through gates, ensure gates are 
fully closed behind you; gently pull handle knob towards you, release: handle knob should spring back 
to prevent handle turning. Do not use the WR machine if handle knob is damaged or sticking. 

6.

  

Cordon off work area in accordance with guidelines. 

7.

  

Safe working load for the WR machine is 1 person only plus tools with a total of 150kg including 
person. Never exceed the safe working load. 

 

NORMAL OPERATION 
1.

  

The WR machine must only be used on hard surfaces not sloping more than 3°. Ensure a person is 
available at ground level to assist in case of emergency. 

2.

  

Position the WR machine under application. Check for any overhead obstructions or dangers. 

3.

  

Check spirit level on the WR machine chassis to ensure the WR machine is level up to 3°. Do not use 
the WR machine unless bubble remains within 3° circle. 

4.

  

To use the WR machine, step into platform through gates. Ensure gates are fully closed behind you. 
Gently pull operating handle knob towards you; turn handle clockwise to elevate. Always check for 
overhead obstructions or dangers. To stop elevation: stop turning handle; release handle knob. Turn 
handle anti-clockwise (counter-clockwise) to descend. 

 

Never attempt to move the WR machine when elevated 

 

EMERGENCY LOWERING OPERATION 

Never attempt to recover the WR machine/operator if there is any possibility the WR machine is contacting 

any live wiring/cabling and is therefore potentially ‘live’.

 

Never operate the emergency lowering without a person in the platform otherwise serious injury may 
result. 

The Emergency Lowering procedure is for lowering the platform from height with an incapacitated operator 
in the platform and for no other purpose. 

1.

  

Remove emergency operation tool located on chassis. If tool is held captive with tie-wrap safety tag 
then break tag to release tool. 

2.

  

Follow instructions on Emergency Lowering Procedure instruction label and on page 8 of this manual. 

 

 

 
 
 