background image

Before starting installation, download the product manual from www.abb.

com/solarinverters. Choose the correct country, string inverters, single phase, 

choose the product and proceed to the “download” section.

Read and follow all safety and installation instructions to avoid disabling any 

safety features or making the warranty invalid.   

Quick installation guide

UNO-DM-3.3/3.8/4.6/5.0-TL-PLUS-US-Q

(from 3.3 to 5.0 kW)

ABB solar inverters

Inverter Models and Components

2.

EN

Mounting Instructions

4.

Installation location 

3.

7.

Input connection (DC) 

6.

Rapid Shutdown

5.

Clamps terminal use

This installation guide covers 4 inverter models of different power levels: 3.3 kW, 3.8 kW, 4.6 kW and 5.0kW.

For each model, the following variant is available:

UNO-DM-3.3-TL-PLUS-US-SB-RA-Q;   UNO-DM-3.8-TL-PLUS-US-SB-RA-Q;   UNO-DM-4.6-TL-PLUS-US-SB-RA-Q;   UNO-DM-5.0-TL-PLUS-US-SB-RA-QU*

Models equipped with Wireless communication,DC disconnection switch,Rapid Shutdown Power Supply and Arc Fault Detector

*Unbalanced input channels (only with 5kW models, refer to the datasheet or product manual)

Main components

02

LED panel

10

UNO-DM-PLUS Ethernet COM KIT or  

UNO-DM-COM KIT board (optional)

16

Protective Earth (PE) connection 

point

22

Lock screw position

04

Inverter front cover

11

Inverter

17

Conduit drill out sizes 3/4”, 1” (drill out 

markings on back side)

23

Power supply for rapid shutdown 

(RSD) terminal blocks

05

Wiring box front cover

12

DC input terminal blocks 

(two MPPT)

18

lower flange

24

Locking Screw

06

DC disconnect switch

13

AC output terminal blocks

19

1/2” communication conduit 

drill out

07

Wall bracket

14

Wiring box

20

Markings for 3/4” or 1” conduit 

drill outs

09

Heatsink

15

Wi-Fi antenna (-B models only)

21

Opening for 3/4” AC conduit

Installation site and position

 -

Refer Datasheet/Manual to confirm that the environmental specifications have been met 

 -Do not install the inverter in full sun.  If needed, use a sun shade to minimize solar 

irradiation, especially for temperatures over 104°F/40°C.

 -Do not install in closed spaces where air does not circulate freely

 -

Always ensure that the flow of air around the inverter is not blocked, so as to prevent 

overheating.

 

-

Do not install the equipment near flammable substances (minimum distance: 10 ft).

 

-

Do not install the equipment on wooden walls or other flammable substances.

 - Do not install in inhabited rooms or where the prolonged presence of people or animals 

is expected, because of the inverter’s noise level during operation. The sound level 

is heavily influenced by its location (for example, the surface around the inverter, the 

environment, etc.) and grid quality.

 -Install on a wall or strong structure capable of bearing weight

 - 

Install vertically with a maximum inclination as indicated in the figure

 -Maintain minimum clearance from objects blocking air circulation and spacing betwe-

en inverter as indicated in the figures

 -

Ensure sufficient working area in front of the inverter for wiring box access

 -If possible, install at eye level so that the LEDs can be seen easily 

 -Install at a height that takes account of the weight of the equipment

 -Position multiple inverters side-by-side, maintaining minimum clearances 

(measured from the outermost edge of the inverter) 

 -Multiple inverters can also be placed in a staggered arrangement. Minimum 

clearances for staggered arrangements include width of the inverter cover 

plus additional allowances for inverters arranged above or below

 

-

All installations over 6500’ high (2,000 meters) must be assessed by ABB 

Technical Sales to determine the proper datasheet derating

Do not block access to the external AC and DC disconnects. 

Please refer to the warranty terms and conditions and avoid voiding the 

warranty with improper installation.

Mount the inverter following the step-by-step procedure below. 

Do not remove the inverter chassis cover in 

adverse weather conditions (e.g. rain, snow)  

or during periods of high humidity (>95%).

Components included in mounting kit

Q.TY

Wall bracket

1

T20 Wall bracket locking 

screw (to be used when 

lock springs 

02

 on the 

bracket are missing)

2

(Spare part) T20 screw for 

front cover

1

Jumpers for configuring  

paralleled inputs.

1 + 1

In additio

n to what 

is explain

ed in this

 guide, th

e safety a

nd installa

tion inform

ation pro

vided in th

e installat

ion manu

al must be

 read and

 followed

.

The techn

ical docu

mentation

 and the in

terface an

d manage

ment softw

are for th

e product

 are availa

ble at the

 website.

XXXXXXX

XXXX

XXXXXXXX

XXXXXXX

XXXXX

XXXXXXX

ABB solar

 inverter

s

Quick installation guide 

(QIG)

1

- Position the bracket 

07

 so that it is level on the wall or pole

-  It is the installer’s responsibility to choose an appropriate 

number and distribution of attachment points. The 

choice must be based on the type of wall, frame or other 

support, the type of anchors to be used, and their ability 

to support 4 times the inverter’s weight (4x33lbs=132lbs 

for all models).   

Depending on the type and number of attachment 

points, drill the required holes to mount the bracket (see 

figure detail 

A

)

- Secure the bracket to the wall or frame

-  If needed, make conduit cutouts in the wiring box chas-

sis, before the wiring box is put on the wall

-  Carefully lift the inverter and hook it onto the bracket by insert-

ing the two supports in the slots on the inverter (Figure 

B

).

-  Proceed to anchor the inverter to the bracket by installing 

the two (one each side) locking screws (Figure 

B1

). 

If on the bracket are present the lateral lock springs, pro-

ceed to lock the inverter by pressing the lower part toward 

the wall or structure until the two springs on the bracket 

set the inverter in position (Figure 

B2

).

-  Secure the inverter chassis bottom flange to the mounting 

surface using another screw (see Figure detail 

C

). Note 

that the bottom flange is not a load-bearing component.

A

C

B

Confirm the correct polarity in the input strings. 

Confirm there is no ground leakage current in the PV array. 

When exposed to sunlight, the PV panels supply DC direct voltage to the inverter.

The inverter’s DC switch disconnects the DC current from the PV panels. In the “OFF” position the inverter will stop producing power, but 

DOES NOT disconnect the AC from the grid. To prevent electrocution hazards, all the connection operations must be carried out with the 

external AC disconnect switch, downstream of the inverter (grid side), open and locked out.
The transformerless design requires that the PV array to be floating with respect to ground per NEC 690.35.

DC PV string wire must be listed PV wire per NEC 690.35 rated minimum 600V.

PV output conductors (wiring) must consist of sheathed (jacketed) multi-conductor cables or single insulated conductors (wires) which 

must be installed in an approved raceway. These conductors must be isolated from the enclosure and system grounding, as required by 

NEC 690.35.  This is the responsibility of the installer.
Confirm that the maximum PV array short circuit current for each DC input channel is within the inverter specification (see table in Section 

14). Array equipment grounding must be installed per the requirements of the NEC and is the responsibility of the installer. A configuration 

program that can help to correctly size the photovoltaic system is available on at http://www.stringsizer.abb.com.

- Turn the DC switch OFF

- Loosen the four captive screws on the wiring box cover (Torx 20) and remove the cover

-  Pass the DC wires through the openings dedicated to the DC conduit.

Conduit must be sealed using water-tight fittings to maintain NEMA Type 4X enclosure integrity.

Installer should follow conduit manufacturers’ guidelines and best practices.

-  Connect the DC wiring to DC input terminal blocks 

12

. DC wiring terminals are spring pressure type and accommodate a wire size range of 20-8 AWG. 

Connect the strings in either independent or parallel mode, following the appropriate set of instructions below: 

Independent mode configuration 

Parallel mode configuration

 In case of two PV arrays, if each of them has a current rating lower than the 

maximum current rating for a single inverter channel, they may be connected 

as “IND” array, each with its own MPPT. In this case, do nothing with the 

jumper wires which came with the inverters.

-  Connect the positive side of the first PV array to +IN1, and its negative side to -IN1. 

-  Connect the positive side of the second PV array to +IN2 and its negative side to -IN2.

Up to four strings can be connected in independent mode.

-  During commissioning, confirm that the input mode is set to IND.

If connecting a single array, configure the inverter for parallel input mode.

If a PV array’s output current is more than the rating for a single inverter 

channel:

- connect the red jumper wire between the +IN1 and +IN2 terminal block 

inputs. Then connect the jumper wire black wire between the -IN1 and -IN2 

terminals. During commissioning remember to set the input mode to PAR.

- Connect the array to the IN1 (MPPT1) and IN2 (MPPT2) input positions, 

running separate wires for positive (+) and negative (-) for each array. 

CAUTION

ATTENTION

REFER TO LOCAL CODE

FOR WIRE SIZE

FAIRE RÉFERENCE À LA

LÉGISLATION LOCALE POUR

LA DIMENSION DU CABLE

-IN1

+IN1

-IN2

+IN2

-RSD

+RSD

MPPT1

 String2

MPPT2

 String2

MPPT2

 String1

MPPT1

 String1

CAUTION

ATTENTION

REFER TO LOCAL CODE

FOR WIRE SIZE

FAIRE RÉFERENCE À LA

LÉGISLATION LOCALE POUR

LA DIMENSION DU CABLE

-IN1

+IN1

-IN2

+IN2

PARALLEL

JUMPERS

-RSD

+RSD

MPPT2

MPPT1

07

09

12

23

10

11

06

13

14

15

16

21

04

05

06

02

20

17

19

06

18

22

Bottom view

Front view

Left view

Right view

Back view

24

6

in

4 in

4 in

8

in

NO

OK

NO

OK

OK

OK

OK

OK

OK

OK

OK

5° MAX

5° MAX

NO

NO

CAUTION

ATTENTION

REFER TO LOCAL CODE

FOR WIRE SIZE

FAIRE RÉFERENCE À LA

LÉGISLATION LOCALE POUR

LA DIMENSION DU CABLE

-IN1

+IN1

-IN2

+IN2

1

2

3

-RSD

+RSD

If an RSD device is installed on the plant, the inverter will power-up only if both AC and DC 

are supplied!

The installer must use an external rapid shutdown device compliant with the 2014 NEC. 

Automatic shutdown occurs at the rooftop box when utility power (AC) is lost or when the PV system’s AC 

disconnect switch is opened. In jurisdictions requiring a dedicated activation switch should be installed an 

emergency stop button external to the inverter. 

The wiring box has 24Vdc (0.4A max) on a spring-loaded terminal block designed to power-up an external 

RSD device.

The wire size range of RSD terminals is 26-12 AWG.

-  Connect the RSD device respecting the polarity indicated on each RSD terminal.

6

in

4 in

4 in

8

in

NO

OK

NO

OK

OK

OK

OK

OK

OK

OK

OK

5° MAX

5° MAX

NO

NO

All power conductors will be inserter in spring clamp terminals.

The figure shows an example of how to make the wire connection: 

1) Insert a small flat screwdriver in the slot and lightly press the screwdriver from top to bottom; 

insert the screwdriver until the spring opens.

2) Insert the cable in the spring clamp.

3) Remove the screwdriver.

4) When connections are complete, give each wire a pull test

1.

Labels and Symbols

IMPORTANT SAFETY INSTRUCTIONS

SAVE THESE INSTRUCTIONS -- KEEP IN A SAFE PLACE! 

The installer must read this document in its entirety before installing or commissioning this equipment.

For more detailed information regarding proper installation and use of this product, refer to the product manual located at www.abb.com/solarinverters. The 

labels on the inverter have the markings, main technical data and identification of the equipment and manufacturer. The technical data shown in this quick 

installation guide does not replace that shown on the labels attached to the equipment. 

Symbols used in the guide and on the products

These are nationally recognized test 

laboratory marks showing certification to 

UL 1741 and CSA-C22 No. 107.1-01

System earth conductor (main groun-

ding protective earth, PE)

ø

Phase

Hazardous voltage

Equipment Grounding Conductor 

(EGC)

 

   Direct and alternating currents, 

respectively

General warning - Important safety 

information

10

Stored energy discharge time

+    -

Positive pole and negative pole of the 

input voltage (DC)

Hot surfaces

Consult product manual

- This device complies with Part 15 of the FCC Rules. Operation is subject to the following two conditions: 

(1) this device may not cause harmful interference, and (2) this device must accept any interference received, including interference that may cause undesired operation.

APPLY HERE

THE WIRELESS

 IDENTIFICATION LABEL

BCM.V2P24.0

Reviews: