ONLITE – Central CPS
Quick commissioning
Issue date: 11/07
Page 2 of 2
6.2) Configuring and addressing lamps for DALI single monitored sub-distributions
(see also commissioning notes chapter 4.8)
a) Assign lamp addresses (circuit 1 to n)
b) Set lamp parameters (description, etc.)
c) If, on the part of the customer, the lamps should be grouped, the assignment is done during the
addressing procedure.
d) Only required if groups have been created:
The group switch functions are assigned in the selection "Group configuration".
Configuring lamps and assigning lamps to groups, if required
3
Done
7.) Check
system
(see also commissioning notes chapter 5)
a) Check switching to DC emergency mode (release the mains to battery switching in menu
"Test").
b) Perform a manual function test:
‒
Check the result of the function test in the test book.
c) Check the status of each emergency luminary according to the desired switch mode.
d) Check switching to emergency mode (check phase monitor loop according to planning
requirement).
Trigger test directly at the phase monitor.
e) Perform a duration test after the batteries have been charged completely (CPS must be
connected to mains supply at least 10 hours) Observe the operating times of the building.
Perhaps prior consultation is necessary!
Check the result of the duration test in the test book.
f) Write down the software version (the software version can be found on page "System
configuration" under "update").
System check
3
Done