ONLITE – Central CPS
Quick commissioning
QUICK COMMISSIONING
1.) Insert fuses (battery and mains)
(see also commissioning notes chapter 4.1, 4.2 and 4.3)
a) Mains fuses first
b) Battery
fuses
afterwards
Fuses inserted (battery and mains)
3
Done
2.) Enable outgoing circuits
(see also commissioning notes chapter 4.4)
Close outgoing fuses F1 - F20 for L (red) and N (blue) each
Outgoing circuits enabled
3
Done
3.) Login
in
(see also commissioning notes chapter 4.5)
Login to the CPS system
Login performed
3
Done
4.) Create
sub-distributions
(see also commissioning notes chapter 4.6)
a) Enter number of sub-distributions
b) Insert identification / type of SD (DALI or current circuit monitored)
c) If, on the part of the customer, particular switch inputs are required, which should be valid
throughout the SD, these must be entered in the section "special switches" (see also user
manual chapter 8.6)
Sub-distribution(s) created
3
Done
5.) Set up circuits
(see also commissioning notes chapter 4.7)
a) The available circuits must be created for each sub-distribution.
b) If, on the part of the customer, particular switch inputs are required, which should be valid
throughout the circuit, these must be entered in the section "Properties" under "switching logic
1" to switching logic 3" (see also user manual chapter 8.3)
Circuits set up
3
Done
6.) Configure and address lamps
6.1) Configuring lamps for circuit monitored sub-distributions
(see also commissioning notes chapter 4.8)
a) Select a circuit created before
b) Create all lamps which are installed in this circuit (function "new lamp")
c) Set lamp parameters (description, etc.)
d) Repeat steps a) and b) for further circuits
e) Calibrate circuit. For this purpose, select the action "Lamp calibration" in menu Test (see also
user manual chapter 6.6)
Issue date: 11/07
Page 1 of 2