www.zuhne.com
iCHORUS 36 Island Hood
5
INSTALLATION PROCEDURE
INSTALL MOUNTING
PLATE AND ANGLE
IRON
1.
Fix the instruction paper onto
the ceiling. Drill holes as the
paper show.
2.
Put the drywall anchors into
the holes and pick out the
mounting plate and use 12
pcs mounting screws to fix the
plate onto the ceiling.(If for
concrete ceiling, pls use the 8
pcs of explode screws).
3.
Put out the 8 pcs of angle iron,
use 8 pcs of mounting
screws(4*14mm) with washers and nuts to fixe 4 pcs angle iron onto the mounting
plate.
4.
Adjust the height X of the chimney( as shown on the picture 1), use
16 pcs of munting screws(4*14mm) with washers and nuts to fixe
the other 4 pcs angle iron onto the angle irons which have been
installed.
INSTALL THE DUCTWORK
NOTE: To reduce the risk of fire, use only metal ductwork.
1. Decide where the ductwork will run between the hood and
the outside.
2. A straight, short duct run will allow the hood to perform
most efficiently.
3. Let the one side of the duct go outside through the hole of
6.7’’ as shown.