Chapter 1 Installation Overview
5.
Take out the static-free bag.
6.
Open up the static-free bag and take out the electronic device.
– End of Steps –
1.4.4 Acceptance and Handover
Steps
1.
Inspection
Check the good's name, model, number etc against the packing list. Verify each goods
according to the following items:
l
Any concave, convex, scratches, peeling, blistering, blot outside the case.
l
Any paint stripping, scratches on the case.
l
Any loosing screw, drop bolts or dislocation.
l
Any missing parts.
Place the goods inspected by categories.
2.
Delivery
The customer representative and engineering supervisor need to sign on the
Unpacking inspection report after the inspection. If the contract specifies the goods be
kept by the customer after the inspection, both parties need to sign on the Unpacking
Inspection Report and transfer the goods to the customer.
– End of Steps –
1.5 Installation Flow
Figure 1-4
shows the flowchart of installing ZXSDR R8882, including PIMDC installation,
device installation, and cabling.