It is recommended that the swing barrier turnstile be installed on a horizontal solid platform with 
50 mm to 100 mm in height, the horizontal angle must not be greater than ±0.7°. 

1.

2.

3.

After installation, check if the connection is done correctly at the connecting points of the ground 
wire, at the connector assemblies and wiring points of the circuits, as well as at each movable part 
of  the  swing  barrier  turnstile.  Any  loose  nuts,  screws  and  other  fasteners  should  be  tightened  in 
time to avoid any failures caused by long-time operations. 

4.

1

1  Installation Requirements 

The installation position of the swing barrier turnstile depends on its size. A distance of 100mm between 
the  swing  barrier  turnstile  and  the  wall  needs  to  be  reserved  for  ease  of  opening  the  top  cover  of  the 
machine to perform maintenance and adjustment. The reference figure is shown below: 

2  Installation Position 

Figure 2-1 SBT2000S Series Dual-lane 

Make sure the ground wire of the system is reliably connected to avoid personal injuries or other 
accidents.

It  is  also  recommended  that  the  swing  barrier  turnstile  should  not  be  used  in  the  corrosive 
environment.

2274.02

2174.02

900

592

800

Summary of Contents for SBT2000S

Page 1: ... Guide SBT2000S Swing Barrier Turnstile Version 1 0 Due to regular upgrades of systems and products ZKTeco could not guarantee exact consistency between the actual product and the written information in this manual ...

Page 2: ...time to avoid any failures caused by long time operations 4 1 1 Installation Requirements The installation position of the swing barrier turnstile depends on its size A distance of 100mm between the swing barrier turnstile and the wall needs to be reserved for ease of opening the top cover of the machine to perform maintenance and adjustment The reference figure is shown below 2 Installation Positi...

Page 3: ...rately to easily distinguish strong and weak power Please invite professional personnel to complete the wiring The device must be connected to the ground 4 Thread the connection wire of the device through the tube before assembly Material A PVC anti fire and insulation tube diameter 25mm standard three core power extension wire tether cable random configuration M12 expansion screws included in the p...

Page 4: ...ew hole at the centre of the stand and the edge of the chassis base on the ground according to the sizes as shown on the Figure 4 1 1 2 3 Drill the holes with Ф14 and embed M12 anchor screws or expansion screws As shown on the Figure 4 2 3 Figure 4 2 Figure 4 1 1 Drill hole 2 Implantation of the screw 3 Fix screw SBT2000S 148 51 ...

Page 5: ...wing barrier turnstile is AC100V 120V 200V 240V and its master and slave are connected by an 2 core cable signal and a 2 core cable power When installing the swing barrier turnstile the user only needs to connect it to the corresponding ports Note that the PVC conduits are laid 100mm under the ground with the height of the exposed part not exceeding 100mm In addition the conduit outlet is bent bac...

Page 6: ... the same time check if the indicators work properly If everything works fine you can tighten the screws and fix the device If an exception occurs please contact your vendor 7 It is recommended that a warning line be marked on the ground after installing the device so as to prompt the pedestrian to stand behind the warning line when swiping the card As shown in Figure 4 4 ...

Page 7: ...5 Wiring Diagram Below is the wiring diagram 6 ...

Page 8: ......