COMMISSIONING THE SYSTEM, INCLUDING P.S.E. 

 

The commissioning of this fire alarm system should be performed by a qualified 
commissioning engineer, who has an understanding of sections 2,3,& 4 of BS5839-
1:2002+A2:2008 (i.e. Design considerations, Limitations of false alarms, Installation 
recommendations) 

 

The system layout drawing should be checked for accuracy & stored in a safe place, 
accessible to any fire officer. 

 

The Fire Alarm System Summary (Page 2) should be checked for accuracy. 

 

The fire alarm log book contact details should be checked for completeness.  

 

The insulation of cables should be checked in accordance with BS5839-1:2002+A2:2008 
clause 38.2 for compliance. 

 

The Earthing should be checked in accordance with BS5839-1:2002+A2:2008 clause 38.2 for 
compliance. 

 

The PSE mains feed from a 3A spur should be checked.

 It should be protected by an over 

current device (MCB) NOT an earth leakage device (RCD). 

 

The PSE Charger voltage should be checked & adjusted if necessary (27.6 with batteries 
disconnected). 

 

The battery voltage should be checked (should be between 24 & 27V) 

 

All call points & detectors can signal an alarm condition and indicate the correct zone (and 
text message) on the fire alarm panel. 

 

The Sound pressure level throughout the building should be checked for compliance with 
the recommendations of BS5839-1:2002+A2:2008  clause 16.2 

 

Any deviations from BS5839-1:2002+A2:2008 clause 7.2 should be listed in the Certificate 
of Installation & Commissioning. 

 

The Certificate of Installation & Commissioning should be completed, and the whole user 
manual passed to the relevant person on site. (They should be given a brief training on the 
basic operation of the FACP) 

DESIGN, INSTALLATION & COMMISSIONING CERTIFICATES 

The guidelines in BS5839-1:2002+A2:2008 say that each stage of the system design and installation 
should have a separate certificate. Before this User Manual is handed over to the relevant 
person(s) on site, the following certificates (or the relevant company’s equivalent) should be 
completed by the system designer, the installation engineer and the commissioning engineer.  The 
System Description sheet should also be completed on Page 2 as should the relevant parts of the 
Log Book section on Page 3. 

The user, or responsible person should then complete the acceptance certificate to acknowledge 
that they have been instructed in the use of the fire alarm, have witnessed that it is operational, 
and have been given all the relevant paperwork (drawings, log book, user manual, etc.) 

 

Summary of Contents for Premier M plus

Page 1: ...PREMIER M PLUS USER MANUAL MAINTENANCE GUIDE LOG BOOK Approved Document No GLT MAN 113 Issue 2 2 Author NRPJ Date 24 7 2012 8 24 ZONE CONVENTIONAL FIRE ALARM PANEL LOG BOOK CERTIFICATES...

Page 2: ...on of all the rooms and areas contained in each zone QTY SNDR QTY MCP QTY HEADS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 SOUNDER CIRCUIT INFORMATION SOUNDER CIRCUIT SOUNDER CIRCU...

Page 3: ...MAN 113 PAGE 2 Issue 2 2 Author NRPJ Date 24 7 2012 OUTPUT ROUTING INFORMATION TYPE OF OUTPUT CONNECTED WHAT HAPPENS WHEN ACTIVATED FIRE RELAY YES NO FAULT RELAY YES NO F A R E OUTPUT YES NO ADDITIONA...

Page 4: ..._________________________________ System Installed By ______________________________________________________________ System Commissioned By _________________________________________________________ Sy...

Page 5: ...R MANUAL MAINTENANCE GUIDE LOG BOOK Approved Document No GLT MAN 113 PAGE 4 Issue 2 2 Author NRPJ Date 24 7 2012 MAINTENANCE WORK DATE TIME ZONE LOCATION REASON FOR WORK WORK CARRIED OUT ADDITIONAL WO...

Page 6: ...PLUS USER MANUAL MAINTENANCE GUIDE LOG BOOK Approved Document No GLT MAN 113 PAGE 5 Issue 2 2 Author NRPJ Date 24 7 2012 DATE TIME ZONE LOCATION REASON FOR WORK WORK CARRIED OUT ADDITIONAL WORK REQUIR...

Page 7: ...ANTED ALARMS CATEGORIES OF FALSE ALARMS ENVIRONMENTAL FIRE LIKE PHENOMENA INAPROPRIATE ACTION ACCIDENTAL DAMAGE MALICIOUS ACTION GENUINE BELIEF EQUIPMENT FALSE ALARM DATE TIME ZONE LOCATION CAUSE IF K...

Page 8: ...2 CATEGORIES OF FALSE ALARMS ENVIRONMENTAL FIRE LIKE PHENOMENA INAPROPRIATE ACTION ACCIDENTAL DAMAGE MALICIOUS ACTION GENUINE BELIEF EQUIPMENT FALSE ALARM DATE TIME ZONE LOCATION CAUSE IF KNOWN OR ACT...

Page 9: ...cument No GLT MAN 113 PAGE 8 Issue 2 2 Author NRPJ Date 24 7 2012 GENUINE ALARMS AND ALARM SYSTEM FAULTS ALL EVENTS OTHER THAN MAINTENANCE WORK OR FALSE ALARMS DATE TIME ZONE LOCATION DETAILS OF EVENT...

Page 10: ...OG BOOK Approved Document No GLT MAN 113 PAGE 9 Issue 2 2 Author NRPJ Date 24 7 2012 ALL EVENTS OTHER THAN MAINTENANCE WORK OR FALSE ALARMS DATE TIME ZONE LOCATION DETAILS OF EVENT INCLUDING CAUSE IF...

Page 11: ...ints detectors can signal an alarm condition and indicate the correct zone and text message on the fire alarm panel The Sound pressure level throughout the building should be checked for compliance wi...

Page 12: ...hich I we have been responsible complies to the best of my our knowledge and belief with the recommendations of section 2 of BS 5839 1 2002 for the system category described below except for the varia...

Page 13: ...guidance has been provided to the user to enable limitation of false alarms Other measures as follows INSTALLATION COMMISSIONING RECOMMENDATIONS It is strongly recommended that installation and commi...

Page 14: ...ribed below and with the recommendations of BS5839 1 2002 except for the variations if any stated in this certificate Name Block Letters Position Signature Date For on behalf of Address The extent of...

Page 15: ...see clause 7 All equipment operates correctly Installation work is as far as can be reasonably ascertained of an acceptable standard The entire system has been inspected and tested in accordance with...

Page 16: ...by this certificate All installation work appears to be satisfactory The system is capable of giving a fire alarm signal The facility for remote transmission of alarms to an alarm receiving centre op...

Reviews: