Installation & Operation • 13
INSTALLATION & OpERATION
9. When joining a Crystal
™
freezer to a Crystal
™
cooler, both cases should be tilted back with an additional 3/16" of shims under the front
bases after the case is leveled. When joining multiple freezers and coolers in a lineup, the tilt back on the coolers should gradually increase
while working away from the cooler/freezer joint until the last case has an additional 3/8" of shims under the front base and the tilt back on
the freezers should gradually decrease to no additional shims while working away from the cooler/freezer joint (
10. Place additional support shims under any bases or hat channel rails with gaps taller than one shim.
Do not place shims between bases
and hat channel rails. Total height of shims should be less than 3/4".
lineup Assembly
Zero Zone display cases have been designed for continuous display so that multiple cases may be joined together to create a lineup of any
desired length. The lineup will be ready for assembly after removing the packaging material.
A case lineup must be properly aligned, which starts with properly leveling the case (
). It is crucial to use a laser
level to measure the high points in the floor and properly shim each base location.
FIGURE 16: Cooler to Freezer Leveling
Freezer
Cooler
Multiple Freezers
Multiple Coolers
Place shims under each base.
Place shims under each base.
Place shims under each base.
Place shims under each base.