Finally, fix the flat duct insulating elements (7) with a suitable adhesive. 

 

 

7.  Insert the EPP moulded parts (see section 

5.2 Preparatory work for direction-change adapter installation

separated from the direction-change adapter (3) into the duct adapters (8) as blanking plugs. They will protect the 
airways in the embrasure module against contamination until the facade surface is finalised. 

                 

 

8.  Check that all the embrasure module components that have been installed up to this point are securely fixed in 

place. 

  Installation steps while building up the facade 

 

Thermal insulation composite system 

1.  Lay the remaining insulation material blanks around the embrasure module so they fit perfectly with the existing 

insulant. 

                    

 

Install the thermal insulation composite system in such a way that there are no gaps between the 
insulation material and the embrasure module. 

2.  After covering the embrasure module with insulation material up to the same thickness as the final insulating layer, 

the duct adapters (8) – not the duct adapter blanking plugs – in the vertical window reveal must protrude by at least 
the dimension of the planned facade finish compared to the finish of the thermal insulation composite system in the 
area of the recess grooves (see section 

6.1.2 Adapting/shortening the flat ducts

). If the front surfaces of the duct 

adapters (8) are level with the final facade surface, three yellow plaster plugs can be inserted into the front holes of 
each of the duct adapters (8) instead of the blanking plugs in the case of a mineral-based facade surface. To protect 
the airways against contamination, insert the EPP moulded parts separated from the direction-change adapter (3) 

Summary of Contents for ComfoSpot 50

Page 1: ...Design Heizk rper Komfortable Rauml ftung Heiz und K hldecken Systeme Clean Air Solutions Embrasure module installation instructions Zehnder ComfoSpot 50...

Page 2: ...installing the thermal insulation composite system 8 Installing the direction change adapter 8 Adapting shortening the flat ducts 8 Installing the flat ducts duct adapters duct insulating elements 9 I...

Page 3: ...e observed Compliance with the relevant fire protection requirements must be ensured in advance The embrasure module can only be installed with a minimum insulating layer thickness of 120 mm and is to...

Page 4: ...flow is conducted via the lower duct connections discharge grille The OBEN TOP embossing on the EPP housing indicates the prescribed installation position The illustrations show the system as viewed f...

Page 5: ...ns provided that the required installation area for ComfoSpot 50 on the inside of the outer wall is taken into account see section 5 1 Drilling the core hole The unit core hole pipe axis must be posit...

Page 6: ...rried out at least 39 cm on the left 29 cm on the right 70 cm at the front and 20 cm at the top in relation to the pipe axis of the wall mounting pipe viewed from the inside of the outer wall 2 Drill...

Page 7: ...laced with a distance of approx 10 cm to the side and approx 2 cm at the top between the drill hole and the outer edges of the direction change adapter 3 and screwed to the EPP housing using PVC screw...

Page 8: ...remains level and round max permissible deviation from the circular shape 1 5 mm If the tube exceeds these tolerances then it is to be brought in the corresponding form fixed with suitable auxiliary m...

Page 9: ...ade finish of the vertical window reveal 3 If you have selected installation variant 1 or 2 shorten the second flat duct 6 to the same dimension If you have selected installation variants 3 or 4 proce...

Page 10: ...ng in order to make it easier to insert the round profile gasket on the side facing the wall 4 Then carry out the same installation steps for the upper flat duct 6 5 Shorten the length of the four fla...

Page 11: ...mal insulation composite system in such a way that there are no gaps between the insulation material and the embrasure module 2 After covering the embrasure module with insulation material up to the s...

Page 12: ...parts of the duct adapter as follows see section 6 1 2 Adapting shortening the flat ducts 1 After applying the final facade surface carefully cut off the protruding material from the EPP body using a...

Page 13: ...illes 10 2 Place the discharge grilles 10 on the duct adapters 8 and fasten them in place with the M5x16 countersunk screws supplied The waterproof swelling sealing tape which is pre fitted to the bac...

Page 14: ...ons_embrasure module CS50_V0519 EN subject to change Sales International Zehnder Group Deutschland GmbH Almweg 34 77933 Lahr Germany T 49 7821 586 392 sales international zehndergroup com www internat...

Reviews: