York YCIV 0590-1500 50Hz Start-Up Checklist Download Page 10

FORM 201.23-CL1 (309)

10

 

JOHNSON CONTROLS

SUBCOOLIng

Example:

Liquid line pressure =

110 PSIG converted to   

  93°F  (33.9°C)

Minus liquid line temp.   

-87°F  (30.6°C)

SUBCOOLING =  

 

  6°F  (3.3°C)

The subcooling should be adjusted to 5 – 7 

°

F (2.77 – 

3.78

°

C)

This  may  be  difficult  to  measure, 

due to test instrument error and the  

difficulty generally encountered when  

measuring  subcooling  on  systems 

operating  with  very  low  condenser 

subcooling.

1.  Record the liquid line pressure and it’s correspond-

ing temperature, liquid line temperature, and sub-

cooling below:

    SYS 1          SYS 2

Liq Line Press =            

          PSIG (kPa)

Temp = 

             

             °F (°C)

Liq Line Temp =             

             °F (°C)

Subcooling =                 

              °F (°C)

Add or remove charge as necessary to obtain a full sight 

glass fully loaded while keeping subcooling to about 

5-7

°

F (2.77-3.78°C

)

.  After an adjustment is made to 

the charge, the flash tank level may rise or drop from 

the approx. 35% point.  Before another measurement is 

made, allow the level to stabilize. 

After  the  subcooling  is  set,  the  suction  superheat 

should be checked. The superheat should be checked 

only after steady state operation of the chiller has been 

established, and the system is running in a fully loaded, 

stable condition. Correct superheat for a system is 8 - 

12°F (4.45 - 6.67°C

)

 and should be reasonably close to 

the system superheat on the chiller display.

The superheat is calculated as the difference between 

the actual temperature of the returned refrigerant gas 

in  the  suction  line  entering  the  compressor  and  the  

temperature corresponding to the suction pressure as 

shown in a standard pressure/temperature chart.

SUPERHEat

Example:

Suction Temp =   

    

46°F (8°C)

minus Suction Press

30 PSIG converted to Temp  

- 35°F (1°C)

 

   11°F  (6°C)

    The suction temperature should be taken 6” (13 

mm) before the compressor suction service valve, 

and the suction pressure is taken at the compressor 

suction service valve.

    No superheat adjustments are necessary and the 

electronically  controlled  drain  valve  need  not 

be adjusted in the field. Ensure that superheat is 

 

controlling at 

8 - 12

°

F (4.45 - 6.67°C

)

.  The purpose 

of this check is primarily to verify the transducer 

and suction temperature sensors in a system are 

providing reasonably accurate outputs to the chiller 

controls.  It also checks the operation of the Feed 

and Drain Valves.

2.  Record the suction temperature, suction pressure, 

suction  pressure  converted  to  temperature,  and 

superheat of each system below:

       

  SYS 1 

 SYS 2

Suction Press = _______  ______ PSIG (kPa)

SP to Temp     = _______  ______ °F  (°C)

Suction Temp  = _______  ______ °F  (°C)

Superheat       = _______  ______ °F  (°C)

3.  Discharge  superheat  will  typically  run  approx. 

28-30°F.  This can be checked on the micropanel 

display.  If the suction superheat drops very low or 

the economizer feeds liquid into the compressor, 

the superheat will drop sharply to approx. 2-3°F.

LEak CHECkIng

1.  Leak check compressors, fittings, and piping to 

ensure no leaks.

    If the chiller is functioning satisfactorily during 

the initial operating period, no safeties trip and the 

chiller controls chilled liquid temperature; it is now 

ready to be placed into service.

Summary of Contents for YCIV 0590-1500 50Hz

Page 1: ...enser coils with the full operating charge as given in the Technical Data Section Service and Oil Line Valves Open each compressor suction economizer and discharge service valve If valves are of the b...

Page 2: ...ore placing the unit back in service valves should be opened and power must be switched on if power is removed for more than 8 hours for at least 8 hours 24 hours if ambient temperature is below 86 F...

Page 3: ...igerant will be seen in the liquid line sight glass After several minutes of operation and provided a full charge of refrigerant is in the system the bubbles will disappear and be replaced by a solid...

Page 4: ...the sight glass If subcooling is out of range add or remove refrigerant as required to clear the sight glass Do not overcharge the unit Subcooling should be checked with a flash tank level of approxim...

Page 5: ...roperly charged and there are no piping leaks 4 Open each system suction service valve discharge service valve economizer service valve liquid line stop valve and oil line ball valve 5 The oil separat...

Page 6: ...s the cooler Excessive flow may cause catastrophic damage to the evaporator 7 Check the control panel to ensure it is free of foreign material wires metal chips tools documents etc 8 Visually inspect...

Page 7: ...using the arrow keys scroll to the compressor overload settings Verify the Fac tory Set overload potentiometer s on the VSD logic board are set correctly In the unlikely event that they are not set c...

Page 8: ...CONTACT YORK REPRESENTATIVE Programmed Values 10 Program the required operating values into the micro for cutouts safeties etc and record them in the chart below Suction Press Cutout _________________...

Page 9: ...Daily Schedule start and stop times 14 Place the panel in Service mode and turn on each fan stage one by one Assure the fans rotate in the correct direction so air flow exits the top of the chiller 1...

Page 10: ...entering the compressor and the temperature corresponding to the suction pressure as shown in a standard pressure temperature chart SUPERHEAT Example Suction Temp 46 F 8 C minus Suction Press 30 PSIG...

Page 11: ...FORM 201 23 CL1 309 JOHNSON CONTROLS 11 notes...

Page 12: ...861 1001 www york com P O Box 1592 York Pennsylvania USA 17405 1592 Subject to change without notice Printed in USA Copyright by Johnson Controls 2009 ALL RIGHTS RESERVED Form 201 23 CL1 309 Supersede...

Reviews: