3.3 Commissioning
CAUTION!
– Before commissioning the device must be brought to
room temperature.
– At condensation the device must be absolutely dry
before connected to power.
– To avoid overheat during operation the device must not
be laid open to direct sun light.
– After opening the control cabinet or desk, there are
parts with possible dangerous voltage available.
– For all signal connections only screened cables are
permitted.
– Signal cables must not be let within the same cable
shaft as high voltage cables.
3.3.1 VIPA Startup-Manager
As soon as the Panel PC is provided by power supply, the
VIPA
Startup-Manager
will be loaded. At the first startup of the
VIPA
Startup-Manager
the following
start screen
appears.
n
There is a button on the
initial screen
with a counter, which counts
backwards. If you click on this button within this time, the project
will start. If the time expires, the project will start automatically.
With the button [Main] you get to the
selection menu
.
n
A delay time of 5 seconds is default. In the
selection menu
under
[Autostart] you can adjust this time.
There are following buttons in the
selection menu
:
n
Settings
n
Info/Update
n
Autostart
n
Backup
n
Exit
n
Back
Start screen
Selection menu
VIPA HMI
Deployment Panel PC
Commissioning > VIPA Startup-Manager
HB160 | PPC | 67S-PNL0 | GB | 16-22