5 Inspection and maintenance
LS Open Loop Vector Motor 4H42, 4H71, 4H72 Manual Supplement
za-o.2.8.41-us-1.1
June 2022
Page 17
za
-o.
2.
8.
41
-us
-1
.1
5.2
Check the insulation resistance
A check of the insulation resistance after a longer standstill or storage of the system
(> 1 year)! This must be carried out at a winding temperature of +20...+30°C.
Before starting the measurement of the insulation resistance, observe the operating
instructions of the insulation meter used.
1.
Carry out the insulation resistance measurement. The measured voltage is 500 V DC.
–
Minimum insulation resistance for new, cleaned or repaired windings at a refer-
ence temperature of +40°C must be
5 MΩ.
–
The critical specific insulation resistance after long operation time is: 0.5
MΩ/kV.
2.
When reaching or falling below the critical insulation resistance.
Remove the rotor and thoroughly clean and dry the windings of the rotor.
Then carry out another check.