background image

ICAM by Xtralis

ICAM Commissioning Guide

www.xtralis.com

15

5

System Integrity Test

ICAM systems can be tested in a number of different ways. Most sites will require different types of testing for
different customer environments. Before conducting smoke tests you must check to see if the local codes
and standards specify which type of smoke test is to be performed. Local codes and standards may also
require changes to the general instructions below, where local codes and standards are different to the ICAM
suggestions, ALWAYS follow the local codes and standards.

Performance testing is done during commissioning and may be required during service, but is not essential.
We highly recommend pipe integrity testing be performed each year.

Note:

Some tests create a large amount of smoke, so you should take the necessary precautions before you
begin testing.

5.1

Performance-based Smoke Testing

A smoke test is necessary to prove the integrity of the pipe network and to measure the response time. The
type of smoke test required will depend upon the site and the application:

l

Warehouses and open areas can use either a smoke pellet test, a polyurethane mat test, or possibly a
wooden block test. Please check with the local codes and standards to find the most appropriate type of
test for the environment.

l

Very sensitive sites can use the electrical overload (PVC coated wire burn test), or the smouldering test
coil test. (UK customers can refer to BS 6266, BFPSA Code of Practice Appendix A for system
performance test methods).

We recommend that at least two tests are conducted. You must allow the environment to return to the normal
conditions before beginning the second test.

Record the date and the type of smoke test used on the commissioning or testing forms. Please re-read the
detector manuals if you are unsure of how to interpret smoke levels, Alert, Alarm or Fire1.

At a minimum, testing requires that you conduct pipe integrity smoke testing.

5.1.1

Testing and Stratification Problems

In areas with a high roof you can expect the air temperature near the roof to be warmer than the air temperature
at ground level. This can cause the stratification of smoke. Stratification occurs when warm smoke rises until
it reaches a layer of air with the same temperature and then stops rising. This may cause problems as the
smoke may not reach sample points which are mounted on the roof.

As the height of the roof increase you will need a larger distance between the roof and the sampling point to
continue correctly sampling the air. Heights up to 3 m (9 ft) can use standard 25 mm (1 in.) standoffs.

Roof Height (M)

1

2

3

4

5

6

7

8

9

Distance from roof (mm)

30

30

30

100

200

300

400

500

600

For testing purposes you can use a 5.8 kW gas burner or electric heater to add heat to the smoke to make sure
it will reach the roof.

Summary of Contents for ICAM IAS

Page 1: ...ICAM Commissioning Guide May 2018 Document 14972_02 Part Number 29303 ...

Page 2: ......

Page 3: ...quipment damage Xtralis is not responsible and cannot be held accountable for any liability that may arise due to improper use of the equipment and or failure to take proper precautions Only persons trained through an Xtralis accredited training course can install test and maintain the system Liability You agree to install configure and use the products strictly in accordance with the User Manual ...

Page 4: ... before you receive the appropriate training may void the warranty Document Conventions The following typographic conventions are used in this document Convention Description Bold Used to denote emphasis Used for names of menus menu options toolbar buttons Italics Used to denote references to other parts of this document or other documents Used for the result of an action The following icons are u...

Page 5: ...efore going to the Site 7 3 2 ICAM Commissioning Form Prerequisites 7 3 3 Once on Site 7 4 System Configuration and Setting Thresholds 9 4 1 IFT Detector Configuration 10 4 2 ILS Detector Configuration 12 4 3 IAS Detector Configuration 13 5 System Integrity Test 15 5 1 Performance based Smoke Testing 15 5 2 Testing Devices 19 5 3 Documenting Test Results 19 6 Hand Over 21 ...

Page 6: ...ICAM Commissioning Guide ICAM by Xtralis 2 www xtralis com This page is intentionally left blank ...

Page 7: ...ICAM system installation It forges together the elements of designing and installing a pipe network installing the detectors cabling for power and communications and the powering up of the system Your objective and outcome of the commissioning process is to provide a fully functional ICAM system that matches your customers specification ...

Page 8: ...ICAM Commissioning Guide ICAM by Xtralis 4 www xtralis com This page is intentionally left blank ...

Page 9: ...er site Gather site information Obtain a copy of l Pipe network design records l Pipe network installation form l Site plans and pipe layout plans Start to fill in l Commissioning forms l Any regulatory forms required 2 Pre Commissioning Once you are on site l Check cables l Power up system l Preliminary system check 3 Configuration Thresholds l Configure the system l Set thresholds l Record in co...

Page 10: ...ICAM Commissioning Guide ICAM by Xtralis 6 www xtralis com This page is intentionally left blank ...

Page 11: ...o Section 5 1 10 Optional Digital manometer if sample hole pressure is required to be measured l Wide Bore networks Max range 3kpa l Narrow Bore networks 0 20kpa at the end of the recommended length of Microbore Tube You must be aware of the local codes and standards as applicable to the customer site 3 2 ICAM Commissioning Form Prerequisites During the pre commissioning stage you should complete ...

Page 12: ...tors l All LEDs turn on then off about five times and the sounder beeps about five times l Aspirator starts l Fault indicators are activated for current faults l Smoke levels are indicated on the bargraph l System OK LED turns on if there are no faults The detector s may show faults immediately after power up and this is normal Reset the detector s to unlatch the relays and fault LEDs The fault LE...

Page 13: ...ly be configured via the detector s user interface Where possible air flow thresholds and smoke alarm thresholds should be determined using ASPIRE pipe network configuration software When an ICAM detector is powered up for the first time Xtralis VSC will register all detectors as unconfigured All other products will appear under ancillary devices For a detailed explanation of the Xtralis VSC softw...

Page 14: ...ontrol functions require the user to enter an Access Code There are several levels of access 1 Operator 2 Level 1 3 Level 2 4 Level 3 Access Code Levels are downwards applicable for example if a User enters the Level 2 Code they have access at the Operator Level and Level 1 The Operator Access Code is changeable as a parameter in Configuration Mode which requires Level 1 Access The default Access ...

Page 15: ... relating to air flow is set through the CONFIGURE menu option Some of the key parameters are l FLOWDEL Flow Fault Delay 1 to 60 s l FLOWHI FLOWLO High and low air flow limits for declaring a Flow Fault 0 to 200 l SETFAN Fan Speed 3 to 10 Setting Smoke Thresholds Minimum Access Code Required Level 1 Day and night smoke thresholds trace and delay settings for each sector can be set through the SECT...

Page 16: ...LED flashes continuously to indicate the function selected To enable updates to the system enter the three digit access code 510 To enter numbers into the system each number must be sequentially selected in turn For example to select 5 press the CHANGE key six times to illuminate the number 5 LED on the display then press the SELECT button During this operation the CODE LED flashes then the UNLOCK...

Page 17: ...ly for 1 sec to initialize function selection Press and release SELECT key to sequentially step through functions Press and release CHANGE key to modify setting The relevant LED flashes continuously to indicate the function selected To enable updates to the system enter the three digit access code 510 To enter numbers into the system each number must be sequentially selected in turn For example to...

Page 18: ...ICAM Commissioning Guide ICAM by Xtralis 14 www xtralis com This page is intentionally left blank ...

Page 19: ...l Very sensitive sites can use the electrical overload PVC coated wire burn test or the smouldering test coil test UK customers can refer to BS 6266 BFPSA Code of Practice Appendix A for system performance test methods We recommend that at least two tests are conducted You must allow the environment to return to the normal conditions before beginning the second test Record the date and the type of...

Page 20: ...s suitable for the testing of high and enhanced sensitivity environments Smoke is produced by lighting a number of small smoke pellets You will need smoke pellets a tray and a method to time the test If you are testing in an area with a high roof you may also require a radiated heater to fix stratification problems Refer to Section 5 1 1 for further information 1 Ensure that the local fire panel i...

Page 21: ...design Legend A 500mm 20 in B Kitchen foil in tray C 20mm 0 874 in Figure 5 2 Polyurethane Mat Smoke Test 5 1 5 Wire Burn Smoke Testing This test is performed by using a transformer to overload the power running through one meter of PVC coated wire To simulate the early stages of a fire a length of wire is electrically overloaded so that smoke or vapors are driven off This method is suitable for t...

Page 22: ...ng the above test procedure Enter the following results on the commissioning form l Transport Time Introduce smoke at the furthest sampling hole from the detector The time taken in seconds for the smoke to travel to the detector is the transport time If there is a wide variation between the ASPIRE predictions and the test results the pipe network should be checked for leaks blockage and to see tha...

Page 23: ...m 5 2 Testing Devices The outputs for the IFT detectors can be tested using a diagnostic test that is accessed through the TEST OUTPUTS menu function For more information please see the IFT Product Guide 5 3 Documenting Test Results The tests results should be recorded on a copy of the ICAM commissioning forms Once the forms have been completed and signed they should be forwarded along with releva...

Page 24: ...ICAM Commissioning Guide ICAM by Xtralis 20 www xtralis com This page is intentionally left blank ...

Page 25: ...issioning forms are complete and all relevant sections have been filled in l If you have used Xtralis VSC select the Device or Address then select File Print to print out a copy of configuration details and include a copy with the hand over documents l Obtain the relevant signatures l Ensure that relevant attachments have been included with the commissioning form l Make copies of the completed com...

Page 26: ...ICAM Commissioning Guide ICAM by Xtralis 22 www xtralis com This page is intentionally left blank ...

Reviews: