Section 2. Installation
Introduction
This section provides recommendations and procedures for inspecting, installing,
and testing the power supply.
Basic Setup Procedure
See Table 2.1 for a summary of the basic setup procedure and an overall view of the
subsections in this section. Use the procedure as a quick reference if you are familiar
with the installation requirements for the power supply. If you want more
information, each step in the procedure refers to subsequent sections which contain
more details. Execute each step in the sequence given.
Table 2.1
Basic Setup Procedure
See Section 3. Local Operation for instructions for front panel operation, OVP and
OTP, shutdown, and using multiple supplies. You will find remote programming and
monitoring described in Section 4. Remote Operation.
Step # Description
Action
Reference
1
Inspection
Perform an initial physical inspection of
the supply.
“Inspection, Cleaning, and
Packaging” on page 36
2
Installation
Install the supply (bench or rack
mount), ensuring adequate ventilation.
“Location, Mounting, and
Ventilation” on page 39
3
Input Power
Connect AC input power.
“AC Input Power Connection” on
page 40
4
Test
Perform functional tests for voltage
mode operation, current mode
operation, and front panel controls.
“Functional Tests” on page 43
5
Load
Connect the load.
“Load Connection” on page 45
6
Sensing
Connect sensing lines.
“Local and Remote Sensing” on
page 53