Original Operating Instructions
BATx0100-ES-1-400-1
Installation
O_BATx0100-ES-1-400-1_V3.1_GB
Page
45
of
73
3.5.2.7 External Temperature Sensor
Required material:
•
Temperature sensor (e.g. PT100) (not included in scope of delivery)
Figure 20: Cable routing to terminal strip (-X17)
Procedure:
1.
Locate
the terminal strip (-X17) (Figure 20).
2.
Connect
the lines to the terminals (-X17.3) and (-X17.4).
3.6
After Installation
After installation the following items must be checked:
•
No waste packaging, waste and tools were left in the product.
•
No transportation and installation damages occurred.
•
Connection lines and terminals are properly connected and the torque has been
checked.
•
If any of the foregoing is not ensured, the product may be damaged. The
manufacturer disclaims any and all liability for damages resulting from a failure
to following the listed steps in this Section 3.6.
Summary of Contents for BAT 0100-ES-1-400-1 Series
Page 73: ......