Configuration Checklist for Enabling the Gen-2-Gen Mode 

Determine the source priority using the "Source 1 priority" and "Source 2 priority" parameters 

Assign a discrete input to the "Gen-Gen enable" 

LogicsManager

 to release an engine start signal 

A second engine start signal (

LogicsManager

 Parameter 20.18 Engine 1 start) must be configured to a relay out-

put 

The "Cooldown timer" for both engines must be configured correctly 

 

Description of the Gen-2-Gen Functions Depending on the Source Priority 

Source 1 is Prioritized 

If the "Gen-Gen enable" 

LogicsManager

 becomes "True", genset 1 will be started. This will be indicated on the 

display with the "Start engine 1" message. 

 

If genset 1 starts before the configured "S1 start fail delay time" expires, the "Source 1 stable timer" will be start-

ed and the load will be transferred to genset 1. 

Special case: genset 1 doesn't start 

If genset 1 does NOT start within the configured "S1 start fail delay time", a "Start fail S1" failure will be issued, 

genset 2 will be started immediately and the load will be transferred to genset 2. 

Source 2 is Prioritized 

If the "Gen-Gen enable" 

LogicsManager

 becomes "True", genset 2 will be started. This will be indicated on the 

display with the "Start engine 2" message. 

 

If genset 2 starts before the configured "S2 start fail delay time" expires, the "Source 2 stable timer" will be start-

ed and the load will be transferred to genset 2. 

Special case: genset 2 doesn't start 

If genset 2 does NOT start within the configured "S2 start fail delay time", a "Start fail S2" failure will be issued, 

genset 1 will be started immediately and the load will be transferred to genset 1. 

Both Sources are NOT Prioritized (Priority = None) 

If the "Gen-Gen enable" 

LogicsManager

 becomes "True", the gensets 1 and 2 will be started simultaneously. 

This will be indicated on the display with the "Start engines" message. 

 

The first genset which starts becomes the "prioritized" source automatically. The engine start command for the 

other generator (secondary source) will be de-energized. 

Now, the secondary source serves as emergency source in case that the prioritized source fails. 

 

If genset 2 starts before the configured "S2 start fail delay time" expires, the "Source 2 stable timer" will be start-

ed and the load will be transferred to genset 2. 

Special case: both gensets do not start 

If genset 1 and genset 2 do NOT start within the configured "S1 Start fail delay time" or “S2 Start fail delay 

time”, a "Start fail S1" and a "Start fail S2" failure will be issued. Both engine start signals will be disabled again. 

All failures must be acknowledged before a new start attempt may be performed. 

 

Summary of Contents for DTSC-200

Page 1: ...37485A Application Software Version 2 0xxx Manual 37485A DTSC 200 ATS Controller...

Page 2: ...off before disconnecting the battery from the system Electronic controls contain static sensitive parts Observe the following precautions to prevent dam age to these parts Discharge body static before...

Page 3: ...Gen 7 Application Mode Util Util 8 Special Applications 9 Example Application Transfer Delay Util Util 9 Example Application External Permit Closed Transition 10 CHAPTER 3 APPLICATION WIRING 11 Wirin...

Page 4: ...t switch reply wiring closed replies only 11 Figure 3 2 Limit switch reply wiring all replies 12 Figure 3 3 Wiring self powered DIs 13 Figure 4 1 Gen 2 Gen application 14 Figure 5 1 Example transition...

Page 5: ...tion storage and installation as well as careful operation and maintenance NOTE This manual has been developed for a unit fitted with all available options Inputs outputs functions configuration scree...

Page 6: ...ication Mode Util Gen This application mode has the following characteristics The ATS controller monitors a mains sources and a generator source and transfers the load to the generator source in case...

Page 7: ...r monitors two generator sources and transfers the load to the other source in case the regular source fails The ATS controller operates as Slave controller This application is not a stand alone appli...

Page 8: ...ces and transfers the load to the secondary source in case the primary source fails The ATS controller operates as Master controller If Connect to synchronous mains parameter 8820 is enabled the trans...

Page 9: ...he Emergency loads to be transferred first and Non Emergency loads to be transferred second In such a scenario the Transfer delay timers become an important tool to prioritize the loads See the follow...

Page 10: ...application external permit closed transition Setup Parameter Ext permit for cld trans must be set to On to activate this feature Parameter Transfer switch type must be configured to Closed Wire the...

Page 11: ...osed replies only 1 Limit switch mounted on transfer switch indicating S1 position 2 Limit switch mounted on transfer switch indicating S2 position NOTE Important If no voltage is applied to the reply...

Page 12: ...cating S2 open position NOTE Important If no voltage is applied to the reply DI this DI is considered as active by the DTSC i e the limit switch position is considered as reached 24 V at terminal 51 S...

Page 13: ...1 minimum wire size 0 5 mm 20 AWG Now it is possible to energize the discrete inputs against ground Figure 3 3 Wiring self powered DIs 60 59 58 Discreteinput DI 11 Discreteinput DI 10 Discreteinput D...

Page 14: ...2 Gen Application Source 1 Priority Source 2 Priority Application mode must be configured to Gen Gen LogicsManager for Gen Gen enable must be enabled to start the preferred genset LogicsManager flag...

Page 15: ...ndicated on the display with the Start engine 2 message If genset 2 starts before the configured S2 start fail delay time expires the Source 2 stable timer will be start ed and the load will be transf...

Page 16: ...tall a key switch which is wired to a discrete input in this example DI 6 of the DTSC in the front panel Figure 5 1 Example transition mode selection switch wiring The LogicsManager function Delayed m...

Page 17: ...mple In this case it is possible to configure the external synchronization device to close a relay which is wired to a dis crete input in this example DI 7 of the DTSC as long as the transfer switch s...

Page 18: ...d if the unit fails to open the transfer switch from both sources In this case it is possible to configure a discrete output of the DTSC 200 in this example R 3 to energize when the shunt trip signal...

Page 19: ...lap time has expired and the LogicsManager function Extended parallel time is FALSE the unit tries to open the transfer switch from the previous source If this fails the unit detects an opening failur...

Page 20: ...increases the overlap time The overlap time counter provides a convenient way to monitor the time for which the transfer switch has remained in overlap position for the last transfer NOTE Overlap time...

Page 21: ...70565 Stuttgart Germany Phone 49 0 711 789 54 510 Fax 49 0 711 789 54 101 stgt info woodward com Homepage http www woodward com power Woodward has company owned plants subsidiaries and branches as we...

Reviews: