Connecting the Extraction Unit
•
The machine must be connected to an effective extrac-
tion system on-site.
Installation only by a qualified electrician!
•
The two suction nozzles (
S
) at the safety fence and on
the right side of the machine (see
Figure 8) have a
diameter of 120 mm.
•
All parts of the extraction system, incl. hoses, must be
included in the earthing measure.
•
Use a 120 mm diameter suction hose to connect the
suction system to the machine's suction nozzles (
S
).
If flexible suction hoses are used, they
must be flame-retardant.
Figure 8: Suction nozzle
•
The extraction system for chips and dust must have an extraction capacity of at least 1800 m
3
/h at a speed
of 25 ... 30 m/s.
6.6.1
Automatic switching of the Extraction System (Option)
If this option is present, additional contacts are available to which two signal generator lines can be connected
for automatic switching of the extraction system.
•
Order designation:
SPM 2-1000-004
The wiring diagram for the connection assignment is enclosed with the machine when this option is ordered.
S
•
The air velocity must be checked before initial commissioning and after significant changes.
•
The extraction system must be checked daily for obvious defects after initial commissioning
and monthly for effectiveness.
When the machine is switched on, the extraction system must start automatically.