6. Transportation, installation, commissioning and shutdown
6.1 Transportation
Transport the pump unit to its destination carefully and by using suitable aids (e.g. hand-carts
or the like).
6.2 Unpacking
Lift the pump unit out of its packaging carefully and put it on a stable and plane base.
Note!
The pump unit and the components attached in accordance with
the scope of delivery may still contain residues of blue-dyed test oil.
6.3 Installation
The pump unit is prepared for being mounted on floor by means of four screws M8. The
mounting area has to be that stable to be able absorbing the weight of the pump unit in-
cluding the filled container.
In addition, make sure that the mounting surface is plane
.
As for the installation the pump unit take necessary prevent measures to protect the unit from
unintentional shocks.
Drill pattern: Mounting
for M8